== Detector location and plane labeling
+
== Preliminary Schedule ==
 +
9/1 Installation and survey until ~18:00
 +
9/1 18:00 - 9/2 04:00 -- Straight-track data (10 hours)
 +
9/2 04:00 - 9/3 12:00 -- Ramp solenoid magnet (8 hours)
 +
9/3 12:00 - 9/4 06:00 -- Full field data: tracking mode (18 hours)
 +
9/4 06:00 - 9/5 10:00 -- Full field data: TRD mode
 +
 
 +
== Detector location and plane labeling ==
  
 
[https://halldweb.jlab.org/wiki/images/4/45/GEM_TRD_setup_Aug2020.pdf Lubomir's presentation]
 
[https://halldweb.jlab.org/wiki/images/4/45/GEM_TRD_setup_Aug2020.pdf Lubomir's presentation]
Line 17: Line 24:
 
** 8 hours: standard FCAL-BCAL trigger for alignment data
 
** 8 hours: standard FCAL-BCAL trigger for alignment data
  
==== Full GEM readout: tracking mode ====
+
==== Full-field data: tracking mode ====
 
* With the aligned GEM/TRD collect data for track extrapolation validation and multi-plane tracking directly upstream of DIRC
 
* With the aligned GEM/TRD collect data for track extrapolation validation and multi-plane tracking directly upstream of DIRC
 
* Full solenoid field sample at the beam-center TRD positions with the full GEM readout for tracking and alignment studies
 
* Full solenoid field sample at the beam-center TRD positions with the full GEM readout for tracking and alignment studies
 
** Standard GlueX running conditions at 150nA, 250 nA and 350nA
 
** Standard GlueX running conditions at 150nA, 250 nA and 350nA
 
** 2 hours: focused FCAL trigger in GEM location to verify TRD/GEM signals (raw mode)
 
** 2 hours: focused FCAL trigger in GEM location to verify TRD/GEM signals (raw mode)
** 8 hours: standard FCAL-BCAL trigger for alignment data at 150 nA (low energy TAGH turned on)
+
** 8 hours: standard FCAL-BCAL trigger at 150 nA (low energy TAGH turned on)
** 4 hours: standard FCAL-BCAL trigger for alignment data at 250 nA (low energy TAGH turned off)
+
** 4 hours: standard FCAL-BCAL trigger at 250 nA (low energy TAGH turned off)
** 4 hours: standard FCAL-BCAL trigger for alignment data at 350 nA (low energy TAGH turned off)
+
** 4 hours: standard FCAL-BCAL trigger at 350 nA (low energy TAGH turned off)
  
==== Full GEM readout: TRD mode ====
+
==== Full-field data: TRD mode ====
 
* For TRD pion rejection performance acquire production samples with the TRD in "cluster counting" mode with all the GEM packages read out.
 
* For TRD pion rejection performance acquire production samples with the TRD in "cluster counting" mode with all the GEM packages read out.
 
* Operate TRDs with two different gasses using raw mode (Lubomir and Sergey required)
 
* Operate TRDs with two different gasses using raw mode (Lubomir and Sergey required)
 
** 4 hours: standard FCAL-BCAL trigger
 
** 4 hours: standard FCAL-BCAL trigger

Revision as of 08:10, 1 September 2020


Preliminary Schedule

9/1 Installation and survey until ~18:00 9/1 18:00 - 9/2 04:00 -- Straight-track data (10 hours) 9/2 04:00 - 9/3 12:00 -- Ramp solenoid magnet (8 hours) 9/3 12:00 - 9/4 06:00 -- Full field data: tracking mode (18 hours) 9/4 06:00 - 9/5 10:00 -- Full field data: TRD mode

Detector location and plane labeling

Lubomir's presentation

Calibration datasets

Summary page for Summer 2020 TRD/GEM Commissioning lists the relevant run ranges for the datasets collected below

Straight-track data

  • For alignment of the GEM/TRD we need to acquire production samples with the magnetic field off
  • Straight-track sample at the beam-center TRD positions with the full GEM readout for tracking and alignment studies
    • Standard GlueX no-field measurements with 50nA on 10^-4 amorphous radiator
    • 2 hours: focused FCAL trigger in GEM location to verify TRD/GEM signals (raw mode)
    • 8 hours: standard FCAL-BCAL trigger for alignment data

Full-field data: tracking mode

  • With the aligned GEM/TRD collect data for track extrapolation validation and multi-plane tracking directly upstream of DIRC
  • Full solenoid field sample at the beam-center TRD positions with the full GEM readout for tracking and alignment studies
    • Standard GlueX running conditions at 150nA, 250 nA and 350nA
    • 2 hours: focused FCAL trigger in GEM location to verify TRD/GEM signals (raw mode)
    • 8 hours: standard FCAL-BCAL trigger at 150 nA (low energy TAGH turned on)
    • 4 hours: standard FCAL-BCAL trigger at 250 nA (low energy TAGH turned off)
    • 4 hours: standard FCAL-BCAL trigger at 350 nA (low energy TAGH turned off)

Full-field data: TRD mode

  • For TRD pion rejection performance acquire production samples with the TRD in "cluster counting" mode with all the GEM packages read out.
  • Operate TRDs with two different gasses using raw mode (Lubomir and Sergey required)
    • 4 hours: standard FCAL-BCAL trigger