(Discussion on CPP and GEM-TRD tests)
(Friday, August 28)
Line 17: Line 17:
 
#* 4.27B trigger  
 
#* 4.27B trigger  
 
#* Beam down for 5hr30mn (weather + communication wrath)
 
#* Beam down for 5hr30mn (weather + communication wrath)
#* [https://logbooks.jlab.org/entry/3835884 Lubomir] and [https://logbooks.jlab.org/entry/3835844 Nick] accessed the hall  
+
#* [https://logbooks.jlab.org/entry/3835844 Nick] and [https://logbooks.jlab.org/entry/3835884 Lubomir] accessed the hall  
 
# Report/issues
 
# Report/issues
 
#* [https://logbooks.jlab.org/entry/3835844 DIRC, South Box Group 9 LV current draw]
 
#* [https://logbooks.jlab.org/entry/3835844 DIRC, South Box Group 9 LV current draw]

Revision as of 08:30, 28 August 2020

<- Back to Run Coordination Meetings:Summer2020

Integrated trigger count

GlueX Statistics Run Sheet


MEDCON 5 restrictions (Bob May email)

  1. adhere to counting room capacity restrictions
  2. maintain 6 ft. separation (briefly passing another person inside 6 ft. while moving about the counting room is inevitable and is OK)
  3. wear masks anytime more than one person present in the counting room
  4. at MEDCON 5 the lab has no cafeteria services because eating "cafeteria style" (eating in common from prepared food) is inconsistent with COVID-19 controls. Staging food in the counting room to share is inconsistent with MEDCON 5 COVID-19 controls.
  5. food and drink consumption - because it requires removing face coverings to consume - should be limited to packaged food and drink brought for personal use that is consumed while maintaining at least 6 ft. from the nearest person and ideally, consumed in a separate room from others.

Friday, August 28

  1. Last 24 hours:
    • 4.27B trigger
    • Beam down for 5hr30mn (weather + communication wrath)
    • Nick and Lubomir accessed the hall
  2. Report/issues
  3. Pending issues:
    • TAGM missing channels due to preamp (Nick, Richard). Update
  4. Run plan

Discussion on trigger/DAQ tests for the SRC/CT

  1. Sasha requested 5-6 hours on Sunday to do these tests

Discussion on CPP and GEM-TRD tests

CPP_Test_2020_-_Schedule

  1. Restricted access on 31st, RADCOM sweep will start at 6 am

Media:CPP_GEM_Test_install_schedule_Aug2020.pdf

Thursday, August 27

  1. Last 24 hours:
    • Due to Hall C current increase request, accelerator experimented with the optics => MCC recommended a HARP scan, 1st scan and 2nd scan
    • Production
    1. Many short trips - beam stable for 5 min and then trips
    2. We lost 8hrs ie runs 72873 to 72876 cannot be used in analysis
  2. Report/issues:
  3. Pending issues:
    • TAGM missing channels due to preamp (Nick, Richard). Update
  4. Run Plan

Discussion on trigger/DAQ tests for the SRC/CT

  1. Sasha requested 5-6 hours on Sunday to do these tests

Discussion on CPP and GEM-TRD tests

CPP_Test_2020_-_Schedule

  1. Restricted or controlled access for 31st depends on if there is 1/2 rack available or not

Media:CPP_GEM_Test_install_schedule_Aug2020.pdf