Difference between revisions of "JEF meeting, October 13, 2023"

From GlueXWiki
Jump to: navigation, search
(Agenda)
Line 7: Line 7:
 
*# - signal cables: 1360 short cables, all long cables are ready
 
*# - signal cables: 1360 short cables, all long cables are ready
 
** - signal patch panels are ready
 
** - signal patch panels are ready
** - HV cables: 140 short cables (expect to receive most of them in 1-2 weeks), 36 long cables are in production
+
*# - HV cables: 140 short cables (expect to receive most of them in 1-2 weeks), 36 long cables are in production
** - HV distribution boards: have not yet been ordered (need to check multi-pin connector layout)
+
*# - HV distribution boards: have not yet been ordered (need to check multi-pin connector layout)
** - LV cables: ordered, lead time unclear
+
*# - LV cables: ordered, lead time unclear
** - LV distribution boards: have not yet been ordered (need to finalize design, meeting with Chris and Stephanie on Monday next week)
+
*# - LV distribution boards: have not yet been ordered (need to finalize design, meeting with Chris and Stephanie on Monday next week)
 
* '''[[Testing of PMT dividers]]''' -- Sasha / Vlad
 
* '''[[Testing of PMT dividers]]''' -- Sasha / Vlad
 
* '''Installation of the FCAL2 detector & integration to GlueX''' -- Sasha / Vlad / Hakob
 
* '''Installation of the FCAL2 detector & integration to GlueX''' -- Sasha / Vlad / Hakob
 
* '''Light monitoring system'''
 
* '''Light monitoring system'''
 
*'''Analysis/Simulation'''
 
*'''Analysis/Simulation'''

Revision as of 22:05, 12 October 2023

Meeting time and location:

Agenda

  • Preparation of parts for ECAL -- Sasha
    1. - signal cables: 1360 short cables, all long cables are ready
    • - signal patch panels are ready
    1. - HV cables: 140 short cables (expect to receive most of them in 1-2 weeks), 36 long cables are in production
    2. - HV distribution boards: have not yet been ordered (need to check multi-pin connector layout)
    3. - LV cables: ordered, lead time unclear
    4. - LV distribution boards: have not yet been ordered (need to finalize design, meeting with Chris and Stephanie on Monday next week)
  • Testing of PMT dividers -- Sasha / Vlad
  • Installation of the FCAL2 detector & integration to GlueX -- Sasha / Vlad / Hakob
  • Light monitoring system
  • Analysis/Simulation