JEF meeting, October 13, 2023
From GlueXWiki
Meeting time and location:
- 9:30 am EST (JLab time) remote only
- Connection information
Agenda
- Preparation of parts for ECAL -- Sasha
- - signal cables: 1360 short cables, all long cables are ready
- - signal patch panels are ready [1]
- - HV cables: 140 short cables (expect to receive most of them in 1-2 weeks), 36 long cables are in production
- - HV distribution boards: have not yet been ordered (need to check multi-pin connector layout)
- - LV cables: ordered, lead time unclear
- - LV distribution boards: have not yet been ordered (need to finalize design, meeting with Chris and Stephanie on Monday next week)
- - Optical fibers: received all
- Ongoing projects -- Sasha, all
- Tested and labeled ~250 short signal cables (Recently labeled cables in boxes)
- Final inspection of installed lead glass and lead tungstate modules [2]
- Meeting with the DSG group to discuss their involvement
- Summer Students (2023)
- All spare crystals (many of them are low quality) have been wrapped [3]
- Testing of PMT dividers -- Sasha / Vlad
- - Test setup is ready. About 30 dividers are ready for testing
- Installation of the FCAL2 detector & integration to GlueX -- Sasha / Vlad / Hakob
- Light monitoring system
- Plastic caps have been glued to all fibers
- Returning low-quality crystals to SICCAS -- Sasha
- 11 crystals were wrapped and placed into the box; they are ready for shipment to SICCAS [9]
- Analysis/Simulation
- First look at impact of GEMTRD -- Simon
Minutes
Attendees: Igal, Phil, Arshak, Sasha, Bill, Jon, Zisis, Axel, Olga, Jane, Malte, S.T.
- Big news: all lead glass blocks and crystals have been installed!
- Re-torqued pressing plates, loctite applied
- Final inspection of all installed modules: some small issues with lead glass found (chips close to PMT, glass imperfections, cookie bubbles)
- Bad/broken PMTs being replaced
- Cabling next: will begin in December/January
- Survey ongoing as of meeting, looks good so far
- Inventory of 80 uninstalled crystals: plan to make 5x5 TAC + 5x5 and 3x3 prototypes to put in PS test setup in Hall
- 11 bad crystals packed, ready to be sent back to SICCAS
- All signal cables from flash-ADCs to patch panel are ready
- Short signal cables arriving (have 1360), students working on testing and labeling
- Still missing many dark box cables
- HV cables in production
- LV cables have been ordered, not clear when will arrive
- LV distribution boards: Sasha to meet with engineering group to finalize design
- Have all optical fibers for LMS
- Sasha met with detector support group to discuss their continuing involvement (soldering wires, testing PMT dividers, gluing fibers to crystals,...)
- PMT divider testing to start: working on test setup (expect to go through ~30/day?)
- LMS installation also December/January
- FCAL group working on plexiglas for lead glass LMS
- 3 undergraduate students expected to go to DNP meeting in Hawaii
- Simon presented a first look at the impact of adding a GEMTRD at the exit of the solenoid
- Also added placeholder for inner-TOF detector