Line 27: | Line 27: | ||
* '''[[Testing of PMT dividers]]''' -- Sasha / Vlad / Aoran / Boaxin | * '''[[Testing of PMT dividers]]''' -- Sasha / Vlad / Aoran / Boaxin | ||
** - Testing procedure [https://halldweb.jlab.org/detectors/fcal2/dividers/divider_test_guide.pptx] | ** - Testing procedure [https://halldweb.jlab.org/detectors/fcal2/dividers/divider_test_guide.pptx] | ||
− | ** - Tested | + | ** - Tested 314 dividers [https://halldweb.jlab.org/wiki/index.php/Final_test_of_dividers] (59 last week) |
* '''Installation of the FCAL2 detector & integration to GlueX''' -- Sasha / Vlad / Hakob | * '''Installation of the FCAL2 detector & integration to GlueX''' -- Sasha / Vlad / Hakob | ||
** Detector installation [https://logbooks.jlab.org/book/halld][https://halldweb.jlab.org/detectors/fcal2/installation/photos/install_fcal/students_detector1.jpg][https://halldweb.jlab.org/detectors/fcal2/installation/photos/install_fcal/students_detector.jpg] | ** Detector installation [https://logbooks.jlab.org/book/halld][https://halldweb.jlab.org/detectors/fcal2/installation/photos/install_fcal/students_detector1.jpg][https://halldweb.jlab.org/detectors/fcal2/installation/photos/install_fcal/students_detector.jpg] |
Revision as of 10:03, 17 November 2023
Meeting time and location:
- 9:30 am EST (JLab time) remote only
- Connection information
Agenda
- Preparation of parts for ECAL -- Sasha
- - signal cables: all cables are ready. Received all needed long cables. Need to test redo 4 bundles (48 cables have been tested)
- - signal patch panels are ready [1]
- - HV cables: have received 50 short cables, have been testes and labeled. 440 cables are ready for installation. 36 long cables are in production
- - HV distribution boards: Chris is finalizing design of the distribution board, should order 4 boards soon.
- - LV cables: ordered, lead time unclear
- - LV distribution boards. The design of the LV distribution board has been finalized (discussion with Fernando, the power regulators will not be added to the design)
- - Optical fibers: received all
- Ongoing projects -- Sasha, all
- - Testing and labeling cables (Recently labeled cables in boxes)[2]
- - Prepare modules for the TAC and prototypes (using crystals with some imperfections) [3]
- Wrapped crystals
- Parts for TAC[4].
- Modules for prototype (25 are ready). All parts are ready to assemble 30 CCAL-style modules.
- - All optical fibers are ready for installation. 3-D printed a mounting plate to couple fibers with the integrating sphere [5] (Boby); the plate was also machined; 3-D printing a fiber tray (will be attached to the plate)
- - Installation of the trigger and readout electronics
- - Summer Students (2023)
- Testing of PMT dividers -- Sasha / Vlad / Aoran / Boaxin
- Installation of the FCAL2 detector & integration to GlueX -- Sasha / Vlad / Hakob
- Light monitoring system
- All optical fibers are ready for installation, the mounting plate to the integrating sphere is under production, will be ready soon.
- Analysis/Simulation