** Crystals:  
 
** Crystals:  
 
**: Received 50 crystals from CRYTUR [https://halldweb.jlab.org/wiki/index.php/CRYTUR ], 10 have been recently sent out. Remaining 45 crystals.
 
**: Received 50 crystals from CRYTUR [https://halldweb.jlab.org/wiki/index.php/CRYTUR ], 10 have been recently sent out. Remaining 45 crystals.
**: Wrapped crystals: 10
+
**: Wrapped crystals during last week: 16
 
**: Available for wrapping: 10 CRYTUR
 
**: Available for wrapping: 10 CRYTUR
 
** Received 725 long signal cables
 
** Received 725 long signal cables

Revision as of 17:46, 25 May 2023

eeting time and location:

Agenda

  • Preparation of parts for ECAL modules -- Sasha
    • Crystals:
      Received 50 crystals from CRYTUR [1], 10 have been recently sent out. Remaining 45 crystals.
      Wrapped crystals during last week: 16
      Available for wrapping: 10 CRYTUR
    • Received 725 long signal cables
    • Procurement parts for the LMS:
      16,400 ft of optical fibers delivered to the lab. 7,600 will be delivered in September.
      Expect to receive all plastic caps for the LMS during next week
  • Module fabrication -- Sasha
  • Visual inspections of fabricated modules [2]
    • 715 modules have been checked (273 SICCAS + 442 CRYTUR) [3]
  • Testing and labeling cables
  • Testing of PMT dividers -- Sasha / Vlad
    • Most parts for the active base have been arrived to the lab (including PCBs)
    • All dividers will be ordered during next week (by Chris S.)
  • Installation of the FCAL2 detector & integration to GlueX -- Sasha / Arshak
Discussion of the FCAL2 installation procedures [5]