Difference between revisions of "JEF meeting, May 26, 2023"

From GlueXWiki
Jump to: navigation, search
(Agenda)
(Agenda)
Line 21: Line 21:
 
* '''Visual inspections of fabricated modules [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/19_05_2023/modules_qa.docx] '''  
 
* '''Visual inspections of fabricated modules [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/19_05_2023/modules_qa.docx] '''  
 
**:  715 modules have been checked (273 SICCAS + 442 CRYTUR)  [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/19_05_2023/modules_shelves.jpg]
 
**:  715 modules have been checked (273 SICCAS + 442 CRYTUR)  [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/19_05_2023/modules_shelves.jpg]
* '''[[Testing of PMT dividers]]''' -- Sasha / Vlad / Arshak
+
* '''[[Testing of PMT dividers]]''' -- Sasha / Vlad
** FCAL2 modules with dividers installed on the CCAL [https://logbooks.jlab.org/entry/4140983]
+
** Most parts for the active base have been arrived to the lab (including PCBs)
** Met  with Vlad P. on Tuesday. Fine tuned the divider circuit. Checking/tuning an amplifier; Chris S. ordered some OPS.
+
** All dividers will be ordered during next week
 
* '''Installation of the FCAL2 detector & integration to GlueX''' -- Sasha / Arshak
 
* '''Installation of the FCAL2 detector & integration to GlueX''' -- Sasha / Arshak
 
** [https://halldweb.jlab.org/wiki/index.php/FCAL_Installation Detector installation page]
 
** [https://halldweb.jlab.org/wiki/index.php/FCAL_Installation Detector installation page]

Revision as of 17:39, 25 May 2023

eeting time and location:

Agenda

  • Preparation of parts for FCAL2 modules -- Sasha
    • Crystals:
      Received 50 crystals from CRYTUR [1], 10 have been recently sent out. Remaining 45 crystals.
      Wrapped crystals: 10
      Available for wrapping: 10 CRYTUR
    • Received 725 long signal cables
    • Procurement parts for the LMS:
      16,400 ft of optical fibers delivered to the lab. 7,600 will be delivered in September.
      Expect to receive all plastic caps for the LMS during next week
  • Module fabrication -- Sasha
  • Visual inspections of fabricated modules [2]
    • 715 modules have been checked (273 SICCAS + 442 CRYTUR) [3]
  • Testing of PMT dividers -- Sasha / Vlad
    • Most parts for the active base have been arrived to the lab (including PCBs)
    • All dividers will be ordered during next week
  • Installation of the FCAL2 detector & integration to GlueX -- Sasha / Arshak
Discussion of the FCAL2 installation procedures [5]