Line 16: Line 16:
 
* '''Module fabrication'''  -- Sasha   
 
* '''Module fabrication'''  -- Sasha   
 
<!-- ** [https://halldweb.jlab.org/detectors/fcal2/module_fabrication/status/fcal_fabrication.pdf  Status of fabrication ] -->
 
<!-- ** [https://halldweb.jlab.org/detectors/fcal2/module_fabrication/status/fcal_fabrication.pdf  Status of fabrication ] -->
** Fabricated modules: <span style="color:#FF0000"> Total 1542 </span>
+
** Fabricated modules: <span style="color:#FF0000"> Total 1558 </span>
**: 9 modules fabricated during last week  <!-- [[File:Fab_mod_may_2023.jpg]] -->
+
**: 16 modules fabricated during last week  <!-- [[File:Fab_mod_may_2023.jpg]] -->
**: Available for fabrication: 26
+
**: 42 modules fabricated using 'low quality' crystals for the stacking mockup and 'crunch' tests.
+
 
** [https://docs.google.com/presentation/d/1euIA49SszoQmSM4Lxu1OtZ8OfjltgwzXIbXo6TPEB3s/edit#slide=id.p Report from students]
 
** [https://docs.google.com/presentation/d/1euIA49SszoQmSM4Lxu1OtZ8OfjltgwzXIbXo6TPEB3s/edit#slide=id.p Report from students]
 
* '''Visual inspections of fabricated modules [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/19_05_2023/modules_qa.docx] '''  
 
* '''Visual inspections of fabricated modules [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/19_05_2023/modules_qa.docx] '''  

Revision as of 17:33, 25 May 2023

eeting time and location:

Agenda

  • Preparation of parts for FCAL2 modules -- Sasha
    • Crystals:
      Received 50 crystals from CRYTUR [1], 10 have been recently sent out. Remaining 45 crystals.
      Wrapped crystals: 10
      Available for wrapping: 10 CRYTUR
    • Received 725 long signal cables
    • Procurement parts for the LMS:
      16,400 ft of optical fibers delivered to the lab. 7,600 will be delivered in September.
      Expect to receive all plastic caps for the LMS during next week
  • Module fabrication -- Sasha
  • Visual inspections of fabricated modules [2]
    • 160 modules checked [3]
  • Testing of PMT dividers -- Sasha / Vlad / Arshak
    • FCAL2 modules with dividers installed on the CCAL [4]
    • Met with Vlad P. on Tuesday. Fine tuned the divider circuit. Checking/tuning an amplifier; Chris S. ordered some OPS.
  • Installation of the FCAL2 detector & integration to GlueX -- Sasha / Arshak
Discussion of the FCAL2 installation procedures [6]