Difference between revisions of "JEF meeting, May 10, 2024"

From GlueXWiki
Jump to: navigation, search
(Agenda)
Line 23: Line 23:
 
** [https://halldweb.jlab.org/wiki/index.php/FCAL_Installation Detector installation page]
 
** [https://halldweb.jlab.org/wiki/index.php/FCAL_Installation Detector installation page]
 
*** (links from the previous meetings [https://logbooks.jlab.org/book/halld][https://halldweb.jlab.org/detectors/fcal2/installation/photos/install_fcal/students_detector1.jpg][https://halldweb.jlab.org/detectors/fcal2/installation/photos/install_fcal/students_detector.jpg])
 
*** (links from the previous meetings [https://logbooks.jlab.org/book/halld][https://halldweb.jlab.org/detectors/fcal2/installation/photos/install_fcal/students_detector1.jpg][https://halldweb.jlab.org/detectors/fcal2/installation/photos/install_fcal/students_detector.jpg])
** '''Preparation for beam tests with the PS'''
+
** '''Beam tests with the PS'''
***  measure shower beam profile  
+
***  measure shower beam profile and reconstruction in the crystal/LG transition region
***   shower reconstruction between PbWO4 and LG
+
*** (install prototype with 5x5 PbWO4 modules  + ? LG)
 
** '''Other hardware projects'''
 
** '''Other hardware projects'''
 
*** --prototype of the ECAL veto counter
 
*** --prototype of the ECAL veto counter
*** --study shower profile using PS (also transition region between lead tungstate and LG modules (?) )
 
 
*'''FCAL2 poster for open house?'''
 
*'''FCAL2 poster for open house?'''
** JEF/ECAL/FCAL poster   
+
** JEF/ECAL/FCAL poster (Laveen + students)  
 
*'''Analysis/Simulation'''
 
*'''Analysis/Simulation'''

Revision as of 08:36, 10 May 2024

Meeting time and location:

Agenda

  • Preparation of parts for ECAL -- Sasha
    • - signal cables and 2 patch panels [1] - done
    • - HV short cables: done
    • - HV long cable, 18 ready (out of 36)
    • - HV distribution boards: not designed
    • - LV cables: waiting for about 20 cables
    • - LV distribution boards [2]. One board out of 4 is ready
    • - LED: the prototype of the LED board has been received. Chris will populate it with components
  • Ongoing projects
  • Testing of PMT dividers -- Sasha / Vlad / George / Mindy
    • - Testing procedure [3]
    • - All dividers have been fabricated and tested by George [4]
      • Continue removing regulators from the PCB (about 70 regulators have been removed, require re-test divider)
  • Installation of the FCAL2 detector & integration to GlueX -- Sasha / Vlad / Hakob / Laveen
    • Installation of the LMS has been completed [5]
    • Installation and testing cables and dividers [6] [7]
    • Detector installation page
    • Beam tests with the PS
      • measure shower beam profile and reconstruction in the crystal/LG transition region
      • (install prototype with 5x5 PbWO4 modules + ? LG)
    • Other hardware projects
      • --prototype of the ECAL veto counter
  • FCAL2 poster for open house?
    • JEF/ECAL/FCAL poster (Laveen + students)
  • Analysis/Simulation