  • Preparation of parts for FCAL2 modules -- Sasha
    • Available crystals:
      1450 (modules)
      32 (ready for fabrication)
      40 (installed on CCAL) available on March 20
      (some CCAL crystals from the inner part will not be used for the FCAL2)
      95 expect to receive from CRYTUR in May [1]
      Total 1617
    • Wrapped crystals: 32 (Mindy)
      • George (DSG group) finished with disassembling CCAL modules and removing LMS caps
      (work on preshaping of ESR reflectors for CRYTUR)
      • Mindy (DSG group) solder wires to sockets (while waiting for crystals)
      • Parts. 60 remaining PMT housings and cylinders have been ordered by Tim (should be ready for fabrication in about 2 months)
  • Module fabrication -- Sasha
    • Fabricated modules: Total 1450 (15 modules fabricated since last week)
      Currently available for fabrication: 32
  • Testing of PMT dividers -- Sasha / Arshak
    • Most parts for dividers have been received
    • 25 dividers for the prototype are ready (have to be tested), expect to receive the LV patch panel prototype