** Fabricated modules: <span style="color:#FF0000"> Total 1450 </span> (15 modules fabricated since last week)  
 
** Fabricated modules: <span style="color:#FF0000"> Total 1450 </span> (15 modules fabricated since last week)  
*** [https://halldweb.jlab.org/detectors/fcal2/module_fabrication/status/module_fabrication.pdf All SICCAS 576 + 3 SICCAS]  
+
**: Available for fabrication: 32
*** [https://halldweb.jlab.org/detectors/fcal2/module_fabrication/status/module_fabrication_crytur.pdf 834 CRYTUR], available: 1
+
<!-- *** [https://halldweb.jlab.org/detectors/fcal2/module_fabrication/status/module_fabrication.pdf All SICCAS 576 + 3 SICCAS] -->
*** [https://halldweb.jlab.org/detectors/fcal2/module_fabrication/status/11_11_22 Moving modules to the new lab (EEL108)]
+
<!-- *** [https://halldweb.jlab.org/detectors/fcal2/module_fabrication/status/module_fabrication_crytur.pdf 834 CRYTUR], available: 1 -->
 +
<!-- *** [https://halldweb.jlab.org/detectors/fcal2/module_fabrication/status/11_11_22 Moving modules to the new lab (EEL108)] -->
 
* '''[[Testing of PMT dividers]]''' -- Sasha / Arshak
 
* '''[[Testing of PMT dividers]]''' -- Sasha / Arshak
 
** Most parts for dividers have been received
 
** Most parts for dividers have been received

Revision as of 18:42, 2 March 2023

Meeting time and location:

  • 9:30 am EST (JLab time) remote only
  • Zoom meeting ID: 161 050 9142 Passcode: 004965

Agenda

  • Preparation of parts for FCAL2 modules -- Sasha
    • Available crystals:
      1450 (modules)
      32 (ready for fabrication)
      40 (installed on CCAL) available on March 20
      (some CCAL crystals from the inner part will not be used for the FCAL2)
      95 expect to receive from CRYTUR in May [1]
      Total 1617
    • Wrapped crystals: 32 (Mindy)
      • George (DSG group) finished with disassembling CCAL modules and removing LMS caps
      (work on preshaping of ESR reflectors for CRYTUR)
      • Mindy (DSG group) solder wires to sockets (while waiting for crystals)
      • Parts. 60 remaining PMT housings and cylinders have been ordered by Tim (should be ready for fabrication in about 2 months)
  • Module fabrication -- Sasha
    • Fabricated modules: Total 1450 (15 modules fabricated since last week)
      Available for fabrication: 32
  • Testing of PMT dividers -- Sasha / Arshak
    • Most parts for dividers have been received
    • 25 dividers for the prototype are ready (have to be tested), expect to receive the LV patch panel prototype

during next week. The CCAL prototype should be ready by the end of next week (?)