Line 16: Line 16:
 
**: (work on preshaping of ESR reflectors for CRYTUR)
 
**: (work on preshaping of ESR reflectors for CRYTUR)
 
*** Mindy (DSG group) solder wires to sockets (while waiting for crystals)
 
*** Mindy (DSG group) solder wires to sockets (while waiting for crystals)
 
+
*** 60 remaining PMT housings and cylinders have been ordered by Tim ( should be ready for fabrication in about 2 months)
<!--
+
**[https://halldweb.jlab.org/detectors/fcal2/module_fabrication/wrapped/wrapped_crytur.pdf Wrapped CRYTUR crystals: 835 (ALL available CRYTUR) ]
+
 
+
*** Available for wrapping: 60 SICCAS crystals from CCAL && prototype [https://halldweb.jlab.org/wiki/index.php/All_modules_(with_SICCAS_crystals)_are_removed] [https://halldweb.jlab.org/detectors/fcal2/module_fabrication/wrapped/ccal_crystals.pdf]
+
 
+
*** George (DSG group) started disassembling CCAL modules and removing LMS caps.
+
*** Mindy (DSG group) continues wrapping crystals and soldering wires to sockets
+
**  Disassembling CCAL
+
*** CCAL moved to the ESB
+
*** [[All modules (with SICCAS crystals) are removed]]
+
** [https://halldweb.jlab.org/detectors/fcal2/module_fabrication/status/part_preparation.pdf List of available parts] -->
+
*** Some PMT housing are missing ( > 60, trying to find with Tim)
+
 
* '''Module fabrication'''  -- Sasha
 
* '''Module fabrication'''  -- Sasha
 
<!-- ** [https://halldweb.jlab.org/detectors/fcal2/module_fabrication/status/fcal_fabrication.pdf  Status of fabrication ] -->
 
<!-- ** [https://halldweb.jlab.org/detectors/fcal2/module_fabrication/status/fcal_fabrication.pdf  Status of fabrication ] -->

Revision as of 18:36, 2 March 2023

Meeting time and location:

  • 9:30 am EST (JLab time) remote only
  • Zoom meeting ID: 161 050 9142 Passcode: 004965

Agenda

  • Preparation of parts for FCAL2 modules -- Sasha
    • Available crystals:
      1450 (modules)
      32 (ready for fabrication)
      40 (installed on CCAL) available on March 20
      (some CCAL crystals from the inner part will not be used for the FCAL2)
      95 expect to receive from CRYTUR in May [1]
      Total 1617
    • Wrapped crystals: 32 (Mindy)
      • George (DSG group) finished with disassembling CCAL modules and removing LMS caps
      (work on preshaping of ESR reflectors for CRYTUR)
      • Mindy (DSG group) solder wires to sockets (while waiting for crystals)
      • 60 remaining PMT housings and cylinders have been ordered by Tim ( should be ready for fabrication in about 2 months)
  • Module fabrication -- Sasha
  • Testing of PMT dividers -- Sasha / Arshak
    • Most parts for dividers have been received
    • 25 dividers for the prototype are ready (have to be tested), expect to receive the LV patch panel prototype

during next week. The CCAL prototype should be ready by the end of next week (?)