Difference between revisions of "JEF meeting, June 9, 2023"

From GlueXWiki
Jump to: navigation, search
(Agenda)
 
(3 intermediate revisions by one other user not shown)
Line 14: Line 14:
 
**: - Expect to receive all plastic caps for the LMS today (can start gluing them to fibers during next week)
 
**: - Expect to receive all plastic caps for the LMS today (can start gluing them to fibers during next week)
 
**: - Cutting Tedlar foils, wrapping PMT light guides, etc.  
 
**: - Cutting Tedlar foils, wrapping PMT light guides, etc.  
** - PO submitted for PMT dividers (expect to receive the first batch in the end of June)
+
** PO submitted for PMT dividers (expect to receive the first batch in the end of June)
 
* '''Module fabrication'''  -- Sasha   
 
* '''Module fabrication'''  -- Sasha   
 
<!-- ** [https://halldweb.jlab.org/detectors/fcal2/module_fabrication/status/fcal_fabrication.pdf  Status of fabrication ] -->
 
<!-- ** [https://halldweb.jlab.org/detectors/fcal2/module_fabrication/status/fcal_fabrication.pdf  Status of fabrication ] -->
Line 23: Line 23:
 
** Visual inspections of fabricated modules [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/19_05_2023/modules_qa.docx]   
 
** Visual inspections of fabricated modules [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/19_05_2023/modules_qa.docx]   
 
**:  -1357 modules have been checked (572 SICCAS + 785 CRYTUR)  [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/19_05_2023/modules_shelves.jpg]
 
**:  -1357 modules have been checked (572 SICCAS + 785 CRYTUR)  [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/19_05_2023/modules_shelves.jpg]
** Testing and labeling cables [https://halldweb.jlab.org/wiki/index.php/Testing_and_labeling_cables]
+
** Testing and labeling signal cables (connect flash ADC with the detector distribution panel) [https://halldweb.jlab.org/wiki/index.php/Testing_and_labeling_cables]
 
**: - 725 long signal cables have been tested [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/25_05_2023/boxes_with_labels.jpg]
 
**: - 725 long signal cables have been tested [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/25_05_2023/boxes_with_labels.jpg]
 
**: - [https://halldweb.jlab.org/wiki/index.php/Testing_labeling_cables Cable tester and label maker]
 
**: - [https://halldweb.jlab.org/wiki/index.php/Testing_labeling_cables Cable tester and label maker]
Line 42: Line 42:
 
<!-- ** [https://halldweb.jlab.org/detectors/fcal2/installation/photos Disassembling FCAL] -->
 
<!-- ** [https://halldweb.jlab.org/detectors/fcal2/installation/photos Disassembling FCAL] -->
 
*'''Light monitoring system''' -- Arshak
 
*'''Light monitoring system''' -- Arshak
 
+
**Fiber polisher [https://userweb.jlab.org/~aasatury/Fcal_LMS/IMG_20230605_174857.jpg]
 
* '''Simulations/Analysis'''
 
* '''Simulations/Analysis'''
 
* [https://halldweb.jlab.org/doc-private/DocDB/ShowDocument?docid=6092 Talk at ECT* workshop next week] -- Simon
 
* [https://halldweb.jlab.org/doc-private/DocDB/ShowDocument?docid=6092 Talk at ECT* workshop next week] -- Simon

Latest revision as of 09:39, 9 June 2023

Meeting time and location:

Agenda

  • Preparation of parts for ECAL modules -- Sasha
    • Crystals:
      - Received all crystals from CRYTUR [1].
      - Available for wrapping: 35 CRYTUR
    • Received 1000 long signal cables
    • Procurement parts for the LMS:
      - 16,400 ft of optical fibers delivered to the lab. 7,600 will be delivered in September.
      - Expect to receive all plastic caps for the LMS today (can start gluing them to fibers during next week)
      - Cutting Tedlar foils, wrapping PMT light guides, etc.
    • PO submitted for PMT dividers (expect to receive the first batch in the end of June)
  • Module fabrication -- Sasha
    • Fabricated modules: Total 1572 (remaining 24 + spares)
      - 10 modules fabricated during last week
    • Report from students
  • Ongoing projects -- Sasha, all
    • Visual inspections of fabricated modules [2]
      -1357 modules have been checked (572 SICCAS + 785 CRYTUR) [3]
    • Testing and labeling signal cables (connect flash ADC with the detector distribution panel) [4]
      - 725 long signal cables have been tested [5]
      - Cable tester and label maker
      - 12 bundles of signal cables are ready (out of 100)
    • Removing signal cables from the FCAL [6]
  • Testing of PMT dividers -- Sasha / Vlad
    • All dividers have been ordered (by Chris S.)
    • Preparing setups for testing modules and dividers
  • Proceedures
  • Installation of the FCAL2 detector & integration to GlueX -- Sasha / Arshak
  • Light monitoring system -- Arshak
    • Fiber polisher [9]
  • Simulations/Analysis
  • Talk at ECT* workshop next week -- Simon