(Agenda)
 
(One intermediate revision by one other user not shown)
Line 28: Line 28:
 
** Most parts for the active base have been arrived to the lab (including PCBs)
 
** Most parts for the active base have been arrived to the lab (including PCBs)
 
** All dividers will be ordered during next week (by Chris S.)
 
** All dividers will be ordered during next week (by Chris S.)
** [https://halldweb.jlab.org/wiki/index.php/FCAL_Insert_Module_Fabrication Proceedures]
+
* '''[https://halldweb.jlab.org/wiki/index.php/FCAL_Insert_Module_Fabrication Proceedures]'''
 
* '''Installation of the FCAL2 detector & integration to GlueX''' -- Sasha / Arshak
 
* '''Installation of the FCAL2 detector & integration to GlueX''' -- Sasha / Arshak
 
** [https://halldweb.jlab.org/wiki/index.php/FCAL_Installation Detector installation page]
 
** [https://halldweb.jlab.org/wiki/index.php/FCAL_Installation Detector installation page]
Line 40: Line 40:
 
*'''Light monitoring system''' -- Arshak
 
*'''Light monitoring system''' -- Arshak
 
* '''Simulations/Analysis'''
 
* '''Simulations/Analysis'''
 +
 +
=Minutes=
 +
Attendees:  Bill, Igal, Sasha, Zisis, Arshak, Olga, Susan, Jon, Stjepan, Axel, S.T.
 +
* Received 10 more Crytur crystals + 2 more boxes
 +
* 16 crystals have been wrapped
 +
* SICCAS can send 60-100 potentially poor quality crystals
 +
** Jane's group can do onsite inspections of these crystals beginning of July
 +
* Grand total fabricated modules = 1562
 +
** 1055 have been inspected visually
 +
** Plan to test all modules using dark box
 +
* Sasha + students recovering cables from FCAL for reuse in FCAL-2
 +
* Plan to start restacking FCAL: preparations are ahead of schedule, could begin in 2 weeks?
 +
* Signal cables arriving at the lab
 +
* PMT dividers ordered, expect 4 week lead time for delivery
 +
* Optical fibers for LMS need to be cut and the donuts attached

Latest revision as of 08:03, 5 June 2023

Meeting time and location:

Agenda

Preparation of parts for ECAL modules -- Sasha

    • Crystals:
      Received 60 crystals from CRYTUR [1]. Remaining 35 crystals are expected to be delivered to the Lab in May/June.
      Wrapped crystals during last week: 16
      Available for wrapping: 10 CRYTUR
    • Received 875 long signal cables
    • Procurement parts for the LMS:
      16,400 ft of optical fibers delivered to the lab. 7,600 will be delivered in September.
      Expect to receive all plastic caps for the LMS during next week
  • Module fabrication -- Sasha
  • Visual inspections of fabricated modules [2]
    -1058 modules have been checked (273 SICCAS + 785 CRYTUR) [3]
  • Testing and labeling cables
  • Removing signal cables from the FCAL [5]
  • Testing of PMT dividers -- Sasha / Vlad
    • Most parts for the active base have been arrived to the lab (including PCBs)
    • All dividers will be ordered during next week (by Chris S.)
  • Proceedures
  • Installation of the FCAL2 detector & integration to GlueX -- Sasha / Arshak
Discussion of the FCAL2 installation procedures [7]

Minutes

Attendees: Bill, Igal, Sasha, Zisis, Arshak, Olga, Susan, Jon, Stjepan, Axel, S.T.

  • Received 10 more Crytur crystals + 2 more boxes
  • 16 crystals have been wrapped
  • SICCAS can send 60-100 potentially poor quality crystals
    • Jane's group can do onsite inspections of these crystals beginning of July
  • Grand total fabricated modules = 1562
    • 1055 have been inspected visually
    • Plan to test all modules using dark box
  • Sasha + students recovering cables from FCAL for reuse in FCAL-2
  • Plan to start restacking FCAL: preparations are ahead of schedule, could begin in 2 weeks?
  • Signal cables arriving at the lab
  • PMT dividers ordered, expect 4 week lead time for delivery
  • Optical fibers for LMS need to be cut and the donuts attached