Difference between revisions of "JEF meeting, June 2, 2023"

From GlueXWiki
Jump to: navigation, search
(Created page with "Meeting time and location: *9:30 am EST (JLab time) remote only * [https://halldweb.jlab.org/wiki-private/index.php/JEF_Weekly_Meeting#Connection_information Connection inform...")
 
Line 5: Line 5:
 
=Agenda=
 
=Agenda=
  
*'''Preparation of parts for ECAL modules''' -- Sasha  
+
'''Preparation of parts for ECAL modules''' -- Sasha  
 +
** Crystals:
 +
**: Received 50 crystals from CRYTUR [https://halldweb.jlab.org/wiki/index.php/CRYTUR ]. Remaining 45 crystals are expected to be delivered to the Lab in May/June.
 +
**: Wrapped crystals during last week: 16
 +
**: Available for wrapping: 10 CRYTUR
 +
** Received 725 long signal cables
 +
** Procurement parts for the LMS:
 +
**: 16,400 ft of optical fibers delivered to the lab. 7,600 will be delivered in September.
 +
**: Expect to receive all plastic caps for the LMS during next week
 
* '''Module fabrication'''  -- Sasha   
 
* '''Module fabrication'''  -- Sasha   
 +
<!-- ** [https://halldweb.jlab.org/detectors/fcal2/module_fabrication/status/fcal_fabrication.pdf  Status of fabrication ] -->
 +
** Fabricated modules: <span style="color:#FF0000"> Total 1558 </span>
 +
**: 16 modules fabricated during last week  <!-- [[File:Fab_mod_may_2023.jpg]] -->
 +
** [https://docs.google.com/presentation/d/1euIA49SszoQmSM4Lxu1OtZ8OfjltgwzXIbXo6TPEB3s/edit#slide=id.p Report from students]
 
* '''Visual inspections of fabricated modules [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/19_05_2023/modules_qa.docx] '''  
 
* '''Visual inspections of fabricated modules [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/19_05_2023/modules_qa.docx] '''  
 +
*:  -715 modules have been checked (273 SICCAS + 442 CRYTUR)  [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/19_05_2023/modules_shelves.jpg]
 
* '''Testing and labeling cables'''
 
* '''Testing and labeling cables'''
 +
** [https://halldweb.jlab.org/wiki/index.php/Testing_labeling_cables Cable tester and label maker]
 +
**: - 600 long signal cables have been tested [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/25_05_2023/boxes_with_labels.jpg]
 
* '''[[Testing of PMT dividers]]''' -- Sasha / Vlad
 
* '''[[Testing of PMT dividers]]''' -- Sasha / Vlad
 +
** Most parts for the active base have been arrived to the lab (including PCBs)
 +
** All dividers will be ordered during next week (by Chris S.)
 
* '''Installation of the FCAL2 detector & integration to GlueX''' -- Sasha / Arshak
 
* '''Installation of the FCAL2 detector & integration to GlueX''' -- Sasha / Arshak
 +
** [https://halldweb.jlab.org/wiki/index.php/FCAL_Installation Detector installation page]
 +
** Updates from the meetings with Tim's group [https://halldweb.jlab.org/wiki/index.php/FCAL_2_Design_Meetings]
 +
:: Discussion of the FCAL2 installation procedures [https://halldweb.jlab.org/wiki/index.php/FCAL_2_Installation_Meetings]
 +
** [https://halldweb.jlab.org/wiki/index.php/Distribution_of_signals_and_voltages Final mapping of low-voltage cables]
 +
** Manpower and division of tasks
 +
** [https://halldweb.jlab.org/wiki/index.php/List_of_tasks_and_manpower Projects for summer students]
 +
** [https://halldweb.jlab.org/detectors/fcal2/installation/students_2023/list_of_students_2023.xlsx Summer Students (2023) ]
 +
<!-- ** [https://halldweb.jlab.org/detectors/fcal2/installation/photos Disassembling FCAL] -->
 
*'''Light monitoring system''' -- Arshak
 
*'''Light monitoring system''' -- Arshak
 
* '''Simulations/Analysis'''
 
* '''Simulations/Analysis'''

Revision as of 08:43, 2 June 2023

Meeting time and location:

Agenda

Preparation of parts for ECAL modules -- Sasha

    • Crystals:
      Received 50 crystals from CRYTUR [1]. Remaining 45 crystals are expected to be delivered to the Lab in May/June.
      Wrapped crystals during last week: 16
      Available for wrapping: 10 CRYTUR
    • Received 725 long signal cables
    • Procurement parts for the LMS:
      16,400 ft of optical fibers delivered to the lab. 7,600 will be delivered in September.
      Expect to receive all plastic caps for the LMS during next week
  • Module fabrication -- Sasha
  • Visual inspections of fabricated modules [2]
    -715 modules have been checked (273 SICCAS + 442 CRYTUR) [3]
  • Testing and labeling cables
  • Testing of PMT dividers -- Sasha / Vlad
    • Most parts for the active base have been arrived to the lab (including PCBs)
    • All dividers will be ordered during next week (by Chris S.)
  • Installation of the FCAL2 detector & integration to GlueX -- Sasha / Arshak
Discussion of the FCAL2 installation procedures [6]