Line 19: Line 19:
 
***  26 modules for TAC [https://halldweb.jlab.org/detectors/fcal2/modules_for_prototype/tac_mod.jpg]  and 35 modules [https://halldweb.jlab.org/detectors/fcal2/modules_for_prototype/prot_mod.jpg] for the beam tests are ready
 
***  26 modules for TAC [https://halldweb.jlab.org/detectors/fcal2/modules_for_prototype/tac_mod.jpg]  and 35 modules [https://halldweb.jlab.org/detectors/fcal2/modules_for_prototype/prot_mod.jpg] for the beam tests are ready
 
** -  Preparation of the LMS  
 
** -  Preparation of the LMS  
*** - All fibers are ready for the installation [https://logbooks.jlab.org/entry/4228633]
+
*** - Need to glue Al flange to the optical fiber
*** - Installing light-tight covers on the plastic caps  [https://halldweb.jlab.org/detectors/fcal2/lms/light_tight_caps/lms_lt4.jpg][https://halldweb.jlab.org/detectors/fcal2/lms/light_tight_caps/lms_lt3.jpg][https://halldweb.jlab.org/detectors/fcal2/lms/light_tight_caps/lms_lt1.jpg][https://halldweb.jlab.org/detectors/fcal2/lms/light_tight_caps/lms_lt2.jpg]. All covers have been installed.
+
*** - Ready for installation
*** - Received an optical bench for the integrating sphere; machined to the right size [https://halldweb.jlab.org/detectors/fcal2/lms/installation/inst_sphere1.jpg] [https://halldweb.jlab.org/detectors/fcal2/lms/installation/inst_sphere2.jpg]
+
 
** - Radiation tests of the PMT active base [https://halldweb.jlab.org/wiki/index.php/Active_Base_Radiation_Tests]
 
** - Radiation tests of the PMT active base [https://halldweb.jlab.org/wiki/index.php/Active_Base_Radiation_Tests]
 
** - [https://halldweb.jlab.org/detectors/AL/HallD_Racks Inventory database and GUI for installed electronics ]
 
** - [https://halldweb.jlab.org/detectors/AL/HallD_Racks Inventory database and GUI for installed electronics ]

Revision as of 09:39, 19 January 2024

Meeting time and location:


Agenda

  • Preparation of parts for ECAL -- Sasha
    • - signal cables - done
    • - signal patch panel [1] - done
    • - HV cables: received 165 short cables during this week (1280 in total)
    • - HV distribution boards: in preparation
    • - LV cables: received first article of short cables, production started on Dec. 7, have not received yet.
    • - LV distribution boards. In production
  • Ongoing projects -- Sasha, all
    • - Testing and labeling cables [2], 120 short HV cables testes and labeled during this week.
    • - Prepare modules for the TAC and prototypes (using crystals with some imperfections)
      • 26 modules for TAC [3] and 35 modules [4] for the beam tests are ready
    • - Preparation of the LMS
      • - Need to glue Al flange to the optical fiber
      • - Ready for installation
    • - Radiation tests of the PMT active base [5]
    • - Inventory database and GUI for installed electronics
    • - Summer Students (2023)
  • Testing of PMT dividers -- Sasha / Vlad / Aoran
    • - Testing procedure [6]
    • - Tested 480 dividers ( during this week) [7]
  • Installation of the FCAL2 detector & integration to GlueX -- Sasha / Vlad / Hakob
  • Abstracts for April'24 APS meeting