Difference between revisions of "JEF meeting, December 15, 2023"
From GlueXWiki
(→Agenda) |
(→Agenda) |
||
Line 15: | Line 15: | ||
** - Testing and labeling cables [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/11_3_2023/aoran_cables.jpg ], 80 short HV cables testes and labeled during this week. | ** - Testing and labeling cables [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/11_3_2023/aoran_cables.jpg ], 80 short HV cables testes and labeled during this week. | ||
** - Prepare modules for the TAC and prototypes (using crystals with some imperfections) | ** - Prepare modules for the TAC and prototypes (using crystals with some imperfections) | ||
− | *** 26 modules for TAC and 35 modules for the beam tests are ready | + | *** 26 modules for TAC [https://halldweb.jlab.org/detectors/fcal2/modules_for_prototype/tac_mod.jpg] and 35 modules [https://halldweb.jlab.org/detectors/fcal2/modules_for_prototype/prot_mod.jpg] for the beam tests are ready |
** - Preparation of the LMS | ** - Preparation of the LMS | ||
*** - All fibers are ready for the installation [https://logbooks.jlab.org/entry/4228633] | *** - All fibers are ready for the installation [https://logbooks.jlab.org/entry/4228633] |
Revision as of 10:16, 15 December 2023
eeting time and location:
- 9:30 am EST (JLab time) remote only
- Connection information
Agenda
- Preparation of parts for ECAL -- Sasha
- - signal cables - done
- - signal patch panel [1] - done
- - HV cables: received 165 short cables during this week (965 in total)
- - HV distribution boards: in preparation
- - LV cables: received first article of short cables, production started on Dec. 7, expect to receive the first batch in the beginning of January
- - LV distribution boards. In production
- Ongoing projects -- Sasha, all
- - Testing and labeling cables [2], 80 short HV cables testes and labeled during this week.
- - Prepare modules for the TAC and prototypes (using crystals with some imperfections)
- - Preparation of the LMS
- - Radiation tests of the PMT active base [12]
- - Inventory database and GUI for installed electronics
- - Summer Students (2023)
- Testing of PMT dividers -- Sasha / Vlad / Aoran
- Installation of the FCAL2 detector & integration to GlueX -- Sasha / Vlad / Hakob
- Detector installation [15][16][17]
- Detector survey
- - waiting for survey results
- Detector installation page
- Updates from the meetings with Tim's group [18]
- Meeting with Chris Cuevas regarding installing optical fibers and patch panels
- Installation of electronics [19]
- Lead Glass Efforts -- Malte / Mark / Kevin / Zisis
- Analysis/Simulation