JEF meeting, December 15, 2023

From GlueXWiki
Jump to: navigation, search

eeting time and location:

Agenda

  • Preparation of parts for ECAL -- Sasha
    • - signal cables - done
    • - signal patch panel [1] - done
    • - HV cables: received 165 short cables during this week (965 in total)
    • - HV distribution boards: in preparation
    • - LV cables: received first article of short cables, production started on Dec. 7, expect to receive the first batch in the beginning of January
    • - LV distribution boards. In production
  • Ongoing projects -- Sasha, all
    • - Testing and labeling cables [2], 80 short HV cables testes and labeled during this week.
    • - Prepare modules for the TAC and prototypes (using crystals with some imperfections)
      • 26 modules for TAC [3] and 35 modules [4] for the beam tests are ready
    • - Preparation of the LMS
      • - All fibers are ready for the installation [5]
      • - Installing light-tight covers on the plastic caps [6][7][8][9] Installed 1245 covers.
      • - Received an optical bench for the integrating sphere; machined to the right size [10] [11]
    • - Radiation tests of the PMT active base [12]
    • - Inventory database and GUI for installed electronics
    • - Summer Students (2023)
  • Testing of PMT dividers -- Sasha / Vlad / Aoran
    • - Testing procedure [13]
    • - Tested 480 dividers (50 during this week) [14]
  • Installation of the FCAL2 detector & integration to GlueX -- Sasha / Vlad / Hakob

Minutes

Attendees: Sasha, Vlad, Jane, Aoran, Stjepan, Liping, Jon, Olga, Hakob, S.T.

  • 165 short HV cables arrived
  • Bottleneck in receiving short LV cables: received first article, production started December 7
  • LV distribution board in production, due week of December 18
  • 26 fabricated modules ready for building small prototypes
    • 5x5 array for TAC
    • 5x5 array for measuring shower profile in PS setup
  • Process of making LMS fibers light tight (using heat shrink material) ongoing: 1300 done
  • Optical bench in place for integrating sphere needed for LMS (inside FCAL dark room)
  • Rad-hardness tests done
  • Testing of PMT dividers continue (now up to 480)
    • Found one bad connector, 4-5 bad dividers
  • Updating inventory database with installed electronics
    • New racks added to GUI
  • Working on transalation table (crate-slot-channel <---> detector module)
  • Waiting for plexiglas (LMS for lead glass) to be completed before work on installing LMS for insert