Difference between revisions of "GlueX Target Design Mtg, May 24, 2013"

From GlueXWiki
Jump to: navigation, search
(Agenda)
(Agenda)
 
(3 intermediate revisions by the same user not shown)
Line 4: Line 4:
  
 
*P&I Diagram [[Media:Target P&I.pdf]]
 
*P&I Diagram [[Media:Target P&I.pdf]]
 +
*Controls logic [[Media:Target controls.pdf]]
 
*Dave's SOW [[Media:Target new SOW.pdf]]
 
*Dave's SOW [[Media:Target new SOW.pdf]]
 
*Dave's Calcs [[Media:Target calcs1.pdf]] [[Media:Target calcs2.pdf]]
 
*Dave's Calcs [[Media:Target calcs1.pdf]] [[Media:Target calcs2.pdf]]
*Dave's FMEA [[Media:Target_FMEA.pdf]]
 
 
*Dave's FMEA [[Media:Target latest FMEA.pdf]]
 
*Dave's FMEA [[Media:Target latest FMEA.pdf]]
* Review notes from last week
+
* Review notes from last mtg
  
 
==Notes from last week==
 
==Notes from last week==
Line 14: Line 14:
 
* Discussed Gas system status, vacuum system, cell and scattering chamber and tasks to be done.  The following are the results of the discussion;
 
* Discussed Gas system status, vacuum system, cell and scattering chamber and tasks to be done.  The following are the results of the discussion;
 
** Procurement of gas system components started. Still need piping and relief valves. $40-50K, some components have arrived
 
** Procurement of gas system components started. Still need piping and relief valves. $40-50K, some components have arrived
** Tank may be smaller than originally thought and may be located on the insertion cart
+
** Sizing tank based on min liquid volume possible
** May put valve on tank to purge to vent system  
+
** May put valve on tank to purge to vent system. Stack must be 5' above roof. Jim to work with facilities
** Gas panel work going well
+
** Target to have 1 fill and 1 return line. "kink in return to reduce liquid volume
** Need to determine location for temp purge tank?
+
** Build production configuration to test system with horizontal target
** Jim to talk with facilities on vent stack location
+
 
** Plan to use 20' x 1.5 inch flex line to allow target to be moved in and out of the detector
 
** Plan to use 20' x 1.5 inch flex line to allow target to be moved in and out of the detector
** lakeshore boxes from target group are in PLC controls ordered and some have arrived. Dave ordered remaining controls/cables?
+
** lakeshore boxes from target group are in. PLC controls ordered and some have arrived. Dave to order remaining controls/cables.
 
** Looks like a heat exchanger using LCW/Chilled water most economical for refrig. compressor. Jim working this
 
** Looks like a heat exchanger using LCW/Chilled water most economical for refrig. compressor. Jim working this
** Jim to get with Chris and James on scattering chamber design (some ideas in work) (<15Psig).
+
** Jim to get with Chris and James on scattering chamber design (some ideas in work) (<15Psig). Jim has envelope
 
** Tim ordered vacuum system pump cube (Pfeifer turbo cube). Still need to order gauging.
 
** Tim ordered vacuum system pump cube (Pfeifer turbo cube). Still need to order gauging.
 
** Chris sent out list of all items needed for monitoring/controlling from PLC system
 
** Chris sent out list of all items needed for monitoring/controlling from PLC system
Line 28: Line 27:
 
** Jim to develop H2 vent details
 
** Jim to develop H2 vent details
 
** Insertion cart can be extended upstream 18-24" to get panel and turbo in lower mag field. Jim to finalize design with target group.
 
** Insertion cart can be extended upstream 18-24" to get panel and turbo in lower mag field. Jim to finalize design with target group.
** One target cell is made, will need to make two more
+
** One target cell is made, will need to make two more. Joint in cell to be at 12 oclock. Also, make an aluminum base with 2 line design to test.
** Josh/James have ideas to develop heat shield and work out cold head weight limits. Jim to work with them on the design
+
** Jim to work with Josh/James on the design of the shield and plumbing
 
** Chris working on PLC algorithm and "empty target/fill target" procedure.
 
** Chris working on PLC algorithm and "empty target/fill target" procedure.
 
** FMEA needed. Cannot rely on PLC for personnel safety. Use safety pressure switches to turn off/close vacuum valves, power to compressor and heater.
 
** FMEA needed. Cannot rely on PLC for personnel safety. Use safety pressure switches to turn off/close vacuum valves, power to compressor and heater.
Line 36: Line 35:
 
** need heater on supply line to boil off liquid. It took 3 days to boil off neon from cell.
 
** need heater on supply line to boil off liquid. It took 3 days to boil off neon from cell.
 
** If heaters used, need controls
 
** If heaters used, need controls
** Plan on internal review this June
+
** Plan on internal review this July
** Cell was tested vertically. There is no plan to test horizontally until production components are fabricated.
+
 
** Question came up if UPS power is required for any components. Maybe not if relays shut off compressor if power goes out.
 
** Question came up if UPS power is required for any components. Maybe not if relays shut off compressor if power goes out.
 
** need to review interlocks on P&I
 
** need to review interlocks on P&I
** All need to read Dave M. SOW and comment back to him.
+
** Dave to update SOW

Latest revision as of 14:47, 23 May 2013

Present: Dave Meekins, Jim Fochtman, Mark Ito, Chris Keith, Tim Whitlatch,

Agenda

Notes from last week

  • Discussed Gas system status, vacuum system, cell and scattering chamber and tasks to be done. The following are the results of the discussion;
    • Procurement of gas system components started. Still need piping and relief valves. $40-50K, some components have arrived
    • Sizing tank based on min liquid volume possible
    • May put valve on tank to purge to vent system. Stack must be 5' above roof. Jim to work with facilities
    • Target to have 1 fill and 1 return line. "kink in return to reduce liquid volume
    • Build production configuration to test system with horizontal target
    • Plan to use 20' x 1.5 inch flex line to allow target to be moved in and out of the detector
    • lakeshore boxes from target group are in. PLC controls ordered and some have arrived. Dave to order remaining controls/cables.
    • Looks like a heat exchanger using LCW/Chilled water most economical for refrig. compressor. Jim working this
    • Jim to get with Chris and James on scattering chamber design (some ideas in work) (<15Psig). Jim has envelope
    • Tim ordered vacuum system pump cube (Pfeifer turbo cube). Still need to order gauging.
    • Chris sent out list of all items needed for monitoring/controlling from PLC system
    • Hall D people to discuss what needs to be shut off in hall when target vacuum goes south
    • Jim to develop H2 vent details
    • Insertion cart can be extended upstream 18-24" to get panel and turbo in lower mag field. Jim to finalize design with target group.
    • One target cell is made, will need to make two more. Joint in cell to be at 12 oclock. Also, make an aluminum base with 2 line design to test.
    • Jim to work with Josh/James on the design of the shield and plumbing
    • Chris working on PLC algorithm and "empty target/fill target" procedure.
    • FMEA needed. Cannot rely on PLC for personnel safety. Use safety pressure switches to turn off/close vacuum valves, power to compressor and heater.
    • Pressurization to failure has been done on individual components. Dave does not believe we need to do the entire system to failure. 2nd DA agreement needed.
    • Heater on return line had little effect on enhancing convection - not needed
    • need heater on supply line to boil off liquid. It took 3 days to boil off neon from cell.
    • If heaters used, need controls
    • Plan on internal review this July
    • Question came up if UPS power is required for any components. Maybe not if relays shut off compressor if power goes out.
    • need to review interlocks on P&I
    • Dave to update SOW