GlueX TOF Meeting, August 2, 2012
GlueX TOF Meeting
Thursday, July 19, 2012
10:00 am EDT
JLab: CEBAF Center, F326
Agenda
- Announcements
- Review of last TOF bi-weekly meeting
- Mechanical design
- Prototype status
- TDC Purchase
- Contract Status
- Calibration and Alignment
- Technical Design Report contribution
Communication
Videoconference
- ESNet: 8542553
- EVO: EVO site
- meeting link
- Phone bridge ID: 13 7104
Slides
Talks can be deposited in the directory /group/halld/www/halldweb1/html/talks/2012-3Q
on the JLab CUE. This directory is accessible from the web at https://halldweb1.jlab.org/talks/2012-3Q/ .
Minutes
tof meeting, Aug. 2
fsu sasha paul randall ian jlab beni mark eugene chuck
response and come in
mini tof randall and chuck have gone back and forth making fixtures for doing light guide clamps ready to start making those in next couple of days orders in for brackets that fsu will finish off
having pieces bent
go over
more light guide rod being covered under contract, FSU scintillating bars updated quotes from Eljen only thing that has not been ordered
as part of the entire large quantity quote
absolutely, circulate locally,
doe annjual report due today, then pick up tdr will try different rubbers and foam, memory foam perhaps when things are glued, things will not be perfectly accurate aluminum clamps fixture light guide gluing stand
problem with contract and buying scintillator, should be covered under contract