JEF meeting, December 15, 2023
From GlueXWiki
eeting time and location:
- 9:30 am EST (JLab time) remote only
- Connection information
Agenda
- Preparation of parts for ECAL -- Sasha
- - signal cables - done
- - signal patch panel[1] - done
- - HV cables: received 165 short cables during this week (965 in total)
- - HV distribution boards: in preparation
- - LV cables: received first article of short cables, production started on Dec. 7, expect to receive the first batch in the beginning of January
- - LV distribution boards. In production
- Ongoing projects -- Sasha, all
- - Testing and labeling cables [2], 80 short HV cables testes and labeled during this week.
- - Prepare modules for the TAC and prototypes (using crystals with some imperfections)
- 26 modules for TAC and 35 modules for the beam tests are ready
- - Preparation of the LMS
- - Radiation tests of the PMT active base [8]
- - Inventory database and GUI for installed electronics [9]
- - Summer Students (2023)
- Testing of PMT dividers -- Sasha / Vlad / Aoran
- Installation of the FCAL2 detector & integration to GlueX -- Sasha / Vlad / Hakob
- Detector installation [12][13][14]
- Detector survey
- - waiting for survey results
- Detector installation page
- Updates from the meetings with Tim's group [15]
- Meeting with Chris Cuevas regarding installing optical fibers and patch panels
- Installation of electronics [16]
- Lead Glass Efforts -- Malte / Mark / Kevin / Zisis
- Analysis/Simulation