JEF meeting, October 13, 2023
From GlueXWiki
Meeting time and location:
- 9:30 am EST (JLab time) remote only
- Connection information
Agenda
- Preparation of parts for ECAL -- Sasha
- - signal cables: 1360 short cables, all long cables are ready
- - signal patch panels are ready [1]
- - HV cables: 140 short cables (expect to receive most of them in 1-2 weeks), 36 long cables are in production
- - HV distribution boards: have not yet been ordered (need to check multi-pin connector layout)
- - LV cables: ordered, lead time unclear
- - LV distribution boards: have not yet been ordered (need to finalize design, meeting with Chris and Stephanie on Monday next week)
- - Optical fibers: received all
- Ongoing projects -- Sasha, all
- Tested and labeled ~250 short signal cables Recently labeled cables in boxes)
- Final inspection of installed lead glass and lead tungstate modules [2]
- Meeting with the DSG group to discuss their involvement
- Summer Students (2023)
- Testing of PMT dividers -- Sasha / Vlad
- - Test setup is ready. About 30 dividers are ready for testing
- Installation of the FCAL2 detector & integration to GlueX -- Sasha / Vlad / Hakob
- Light monitoring system
- Analysis/Simulation
- First look at impact of GEMTRD -- Simon