JEF meeting, June 9, 2023
From GlueXWiki
Meeting time and location:
- 9:30 am EST (JLab time) remote only
- Connection information
Agenda
Preparation of parts for ECAL modules -- Sasha
- Crystals:
- Received all crystals from CRYTUR [1].
- Available for wrapping: 35 CRYTUR
- Received 1000 long signal cables
- Procurement parts for the LMS:
- 16,400 ft of optical fibers delivered to the lab. 7,600 will be delivered in September.
- Expect to receive all plastic caps for the LMS today (can start gluing them to fibers during next week)
- PO submitted for PMT dividers (expect to receive the first batch in the end of June)
- Crystals:
- Module fabrication -- Sasha
- Fabricated modules: Total 1572 (remaining 24 + spares)
- 10 modules fabricated during last week
- Report from students
- Fabricated modules: Total 1572 (remaining 24 + spares)
- Ongoing projects
- Visual inspections of fabricated modules [2]
- -1357 modules have been checked (572 SICCAS + 785 CRYTUR) [3]
- Testing and labeling cables
- - Cable tester and label maker
- - 725 long signal cables have been tested [4]
- Removing signal cables from the FCAL [5]
- Visual inspections of fabricated modules [2]
- Testing of PMT dividers -- Sasha / Vlad
- Most parts for the active base have been arrived to the lab (including PCBs)
- All dividers will be ordered during next week (by Chris S.)
- Proceedures
- Installation of the FCAL2 detector & integration to GlueX -- Sasha / Arshak
- Detector installation page
- Updates from the meetings with Tim's group [6]
- Discussion of the FCAL2 installation procedures [7]
- Final mapping of low-voltage cables
- Manpower and division of tasks
- Projects for summer students
- Summer Students (2023)
- Light monitoring system -- Arshak
- Simulations/Analysis
- Talk at ECT* workshop next week -- Simon