JEF meeting, April 21, 2023
From GlueXWiki
Meeting time and location:
- 9:30 am EST (JLab time) remote only
- Zoom meeting ID: 161 050 9142 Passcode: 004965
Agenda
- Preparation of parts for FCAL2 modules -- Sasha
- Available crystals:
- 1450 (modules)
- 32 (ready for fabrication)
- 40 (installed on CCAL)
- (some CCAL crystals from the inner part will not be used for the FCAL2)
- 95 expect to receive from CRYTUR in May [1] Expect to start shipping crystals in the 2nd week of April.
- Total 1617
- Disassemble the CCAL prototype
- Available crystals:
- George (DSG group) unwrapped CCAL modules and removed LMS caps. 21 modules are ready for wrapping. Started working on preshaping ESR reflectors (65 pcs) for CRYTUR.
- Mindy (DSG group) wrapped 17 modules. She continues soldering wires to sockets
- Chris S. is getting quotes for HV and LV cabled.
- Ordered 16,000 ft of optical fibers (need to add 8,000 ft to the PO), discussing delivery schedule.
- Module fabrication -- Sasha
- Fabricated modules: Total 1482
- Currently available for fabrication: 17 (modules will be available during next week)
- Fabricated modules: Total 1482
- Testing of PMT dividers -- Sasha / Arshak
- FCAL2 modules with dividers installed on the CCAL [3]
- Meeting with Vlad P. on Tuesday next week (final check of the dividers, proceed with the order)
- Installation of the FCAL2 detector & integration to GlueX -- Sasha / Arshak
- Detector installation page
- Updates from the meetings with Tim's group [4]
- Manpower and division of tasks
- Projects for summer students
- Summer Students (2023)
- Light Monitoring System -- Arshak
- Simulations/Analysis