Line 10: | Line 10: | ||
** - signal cables - done | ** - signal cables - done | ||
** - signal patch panel [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/10_13_2023/signal_patch_panel.jpg ] - done | ** - signal patch panel [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/10_13_2023/signal_patch_panel.jpg ] - done | ||
− | ** - HV cables: received 165 short cables during this week ( | + | ** - HV cables: received 165 short cables during this week (1280 in total) |
** - HV distribution boards: in preparation | ** - HV distribution boards: in preparation | ||
− | ** - LV cables: received first article of short cables, production started on Dec. 7, | + | ** - LV cables: received first article of short cables, production started on Dec. 7, have not received yet. |
** - LV distribution boards. In production | ** - LV distribution boards. In production | ||
* '''Ongoing projects''' -- Sasha, all | * '''Ongoing projects''' -- Sasha, all | ||
− | ** - Testing and labeling cables [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/11_3_2023/aoran_cables.jpg ], | + | ** - Testing and labeling cables [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/11_3_2023/aoran_cables.jpg ], 120 short HV cables testes and labeled during this week. |
** - Prepare modules for the TAC and prototypes (using crystals with some imperfections) | ** - Prepare modules for the TAC and prototypes (using crystals with some imperfections) | ||
*** 26 modules for TAC [https://halldweb.jlab.org/detectors/fcal2/modules_for_prototype/tac_mod.jpg] and 35 modules [https://halldweb.jlab.org/detectors/fcal2/modules_for_prototype/prot_mod.jpg] for the beam tests are ready | *** 26 modules for TAC [https://halldweb.jlab.org/detectors/fcal2/modules_for_prototype/tac_mod.jpg] and 35 modules [https://halldweb.jlab.org/detectors/fcal2/modules_for_prototype/prot_mod.jpg] for the beam tests are ready |
Revision as of 09:37, 19 January 2024
Meeting time and location:
- 9:30 am EST (JLab time) remote only
- Connection information
Agenda
- Preparation of parts for ECAL -- Sasha
- - signal cables - done
- - signal patch panel [1] - done
- - HV cables: received 165 short cables during this week (1280 in total)
- - HV distribution boards: in preparation
- - LV cables: received first article of short cables, production started on Dec. 7, have not received yet.
- - LV distribution boards. In production
- Ongoing projects -- Sasha, all
- - Testing and labeling cables [2], 120 short HV cables testes and labeled during this week.
- - Prepare modules for the TAC and prototypes (using crystals with some imperfections)
- - Preparation of the LMS
- - Radiation tests of the PMT active base [12]
- - Inventory database and GUI for installed electronics
- - Summer Students (2023)
- Testing of PMT dividers -- Sasha / Vlad / Aoran
- Installation of the FCAL2 detector & integration to GlueX -- Sasha / Vlad / Hakob
- Detector installation [15][16][17]
- Detector survey
- Detector installation page
- Updates from the meetings with Tim's group [18]
- Meeting with Chris Cuevas regarding installing optical fibers and patch panels
- Installation of electronics [19]
- Abstracts for April'24 APS meeting