Difference between revisions of "JEF meeting, October 13, 2023"
From GlueXWiki
(→Agenda) |
(→Agenda) |
||
Line 15: | Line 15: | ||
** - Test setup is ready. About 30 dividers are ready for testing | ** - Test setup is ready. About 30 dividers are ready for testing | ||
* '''Installation of the FCAL2 detector & integration to GlueX''' -- Sasha / Vlad / Hakob | * '''Installation of the FCAL2 detector & integration to GlueX''' -- Sasha / Vlad / Hakob | ||
+ | ** Detector installation [https://logbooks.jlab.org/book/halld][https://halldweb.jlab.org/detectors/fcal2/installation/photos/install_fcal/students_detector1.jpg][https://halldweb.jlab.org/detectors/fcal2/installation/photos/install_fcal/students_detector.jpg] | ||
+ | ** [https://halldweb.jlab.org/wiki/index.php/FCAL_Installation Detector installation page] | ||
+ | ** Updates from the meetings with Tim's group [https://halldweb.jlab.org/wiki/index.php/FCAL_2_Design_Meetings] | ||
+ | ** Discussion of the FCAL2 installation procedures [https://halldweb.jlab.org/wiki/index.php/FCAL_2_Installation_Meetings] | ||
+ | ** [https://halldweb.jlab.org/wiki/index.php/Distribution_of_signals_and_voltages Final mapping of low-voltage cables] | ||
+ | ** Mindy continues with wrapping crystals and soldering wires to sockets. | ||
+ | ** [https://halldweb.jlab.org/wiki/index.php/List_of_tasks_and_manpower Projects for summer students] | ||
+ | ** [https://halldweb.jlab.org/detectors/fcal2/installation/students_2023/list_of_students_2023.xlsx Summer Students (2023) ] | ||
* '''Light monitoring system''' | * '''Light monitoring system''' | ||
*'''Analysis/Simulation''' | *'''Analysis/Simulation''' |
Revision as of 22:15, 12 October 2023
Meeting time and location:
- 9:30 am EST (JLab time) remote only
- Connection information
Agenda
- Preparation of parts for ECAL -- Sasha
- - signal cables: 1360 short cables, all long cables are ready
- - signal patch panels are ready
- - HV cables: 140 short cables (expect to receive most of them in 1-2 weeks), 36 long cables are in production
- - HV distribution boards: have not yet been ordered (need to check multi-pin connector layout)
- - LV cables: ordered, lead time unclear
- - LV distribution boards: have not yet been ordered (need to finalize design, meeting with Chris and Stephanie on Monday next week)
- - Optical fibers: received all
- Testing of PMT dividers -- Sasha / Vlad
- - Test setup is ready. About 30 dividers are ready for testing
- Installation of the FCAL2 detector & integration to GlueX -- Sasha / Vlad / Hakob
- Detector installation [1][2][3]
- Detector installation page
- Updates from the meetings with Tim's group [4]
- Discussion of the FCAL2 installation procedures [5]
- Final mapping of low-voltage cables
- Mindy continues with wrapping crystals and soldering wires to sockets.
- Projects for summer students
- Summer Students (2023)
- Light monitoring system
- Analysis/Simulation