Difference between revisions of "JEF meeting, June 9, 2023"
From GlueXWiki
(→Agenda) |
(→Agenda) |
||
Line 28: | Line 28: | ||
** Removing signal cables from the FCAL [https://halldweb.jlab.org/wiki/index.php/Removing_FCAL_cables_from_the_detector] | ** Removing signal cables from the FCAL [https://halldweb.jlab.org/wiki/index.php/Removing_FCAL_cables_from_the_detector] | ||
* '''[[Testing of PMT dividers]]''' -- Sasha / Vlad | * '''[[Testing of PMT dividers]]''' -- Sasha / Vlad | ||
− | |||
** All dividers have been ordered (by Chris S.) | ** All dividers have been ordered (by Chris S.) | ||
+ | ** Preparing setups for testing modules and dividers | ||
* '''[https://halldweb.jlab.org/wiki/index.php/FCAL_Insert_Module_Fabrication Proceedures]''' | * '''[https://halldweb.jlab.org/wiki/index.php/FCAL_Insert_Module_Fabrication Proceedures]''' | ||
* '''Installation of the FCAL2 detector & integration to GlueX''' -- Sasha / Arshak | * '''Installation of the FCAL2 detector & integration to GlueX''' -- Sasha / Arshak |
Revision as of 08:49, 9 June 2023
Meeting time and location:
- 9:30 am EST (JLab time) remote only
- Connection information
Agenda
Preparation of parts for ECAL modules -- Sasha
- Crystals:
- - Received all crystals from CRYTUR [1].
- - Available for wrapping: 35 CRYTUR
- Received 1000 long signal cables
- Procurement parts for the LMS:
- - 16,400 ft of optical fibers delivered to the lab. 7,600 will be delivered in September.
- - Expect to receive all plastic caps for the LMS today (can start gluing them to fibers during next week)
- - Cutting Tedlar foils, wrapping PMT light guides, etc.
- - PO submitted for PMT dividers (expect to receive the first batch in the end of June)
- Crystals:
- Module fabrication -- Sasha
- Fabricated modules: Total 1572 (remaining 24 + spares)
- 10 modules fabricated during last week
- Report from students
- Fabricated modules: Total 1572 (remaining 24 + spares)
- Ongoing projects -- Sasha, all
- Visual inspections of fabricated modules [2]
- -1357 modules have been checked (572 SICCAS + 785 CRYTUR) [3]
- Testing and labeling cables
- - Cable tester and label maker
- - 725 long signal cables have been tested [4]
- Removing signal cables from the FCAL [5]
- Visual inspections of fabricated modules [2]
- Testing of PMT dividers -- Sasha / Vlad
- All dividers have been ordered (by Chris S.)
- Preparing setups for testing modules and dividers
- Proceedures
- Installation of the FCAL2 detector & integration to GlueX -- Sasha / Arshak
- Detector installation page
- Updates from the meetings with Tim's group [6]
- Discussion of the FCAL2 installation procedures [7]
- Final mapping of low-voltage cables
- Manpower and division of tasks
- Projects for summer students
- Summer Students (2023)
- Light monitoring system -- Arshak
- Simulations/Analysis
- Talk at ECT* workshop next week -- Simon