Difference between revisions of "JEF meeting, May 26, 2023"
From GlueXWiki
(→Agenda) |
(→Agenda) |
||
Line 23: | Line 23: | ||
* '''Testing and labeling cables''' | * '''Testing and labeling cables''' | ||
** [https://halldweb.jlab.org/wiki/index.php/Testing_labeling_cables Cable tester and label maker] | ** [https://halldweb.jlab.org/wiki/index.php/Testing_labeling_cables Cable tester and label maker] | ||
− | **: - 600 long signal cables have been tested [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/ | + | **: - 600 long signal cables have been tested [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/25_05_2023/boxes_with_labels.jpg] |
* '''[[Testing of PMT dividers]]''' -- Sasha / Vlad | * '''[[Testing of PMT dividers]]''' -- Sasha / Vlad | ||
** Most parts for the active base have been arrived to the lab (including PCBs) | ** Most parts for the active base have been arrived to the lab (including PCBs) |
Revision as of 19:12, 25 May 2023
eeting time and location:
- 9:30 am EST (JLab time) remote only
- Connection information
Agenda
- Preparation of parts for ECAL modules -- Sasha
- Crystals:
- Received 50 crystals from CRYTUR [1]. Remaining 45 crystals are expected to be delivered to the Lab in May/June.
- Wrapped crystals during last week: 16
- Available for wrapping: 10 CRYTUR
- Received 725 long signal cables
- Procurement parts for the LMS:
- 16,400 ft of optical fibers delivered to the lab. 7,600 will be delivered in September.
- Expect to receive all plastic caps for the LMS during next week
- Crystals:
- Module fabrication -- Sasha
- Fabricated modules: Total 1558
- 16 modules fabricated during last week
- Report from students
- Fabricated modules: Total 1558
- Visual inspections of fabricated modules [2]
- -715 modules have been checked (273 SICCAS + 442 CRYTUR) [3]
- Testing and labeling cables
- Cable tester and label maker
- - 600 long signal cables have been tested [4]
- Cable tester and label maker
- Testing of PMT dividers -- Sasha / Vlad
- Most parts for the active base have been arrived to the lab (including PCBs)
- All dividers will be ordered during next week (by Chris S.)
- Installation of the FCAL2 detector & integration to GlueX -- Sasha / Arshak
- Detector installation page
- Updates from the meetings with Tim's group [5]
- Discussion of the FCAL2 installation procedures [6]
- Final mapping of low-voltage cables
- Manpower and division of tasks
- Projects for summer students
- Summer Students (2023)
- Light monitoring system -- Arshak
- Simulations/Analysis