** - HV distribution boards: has not yet been designed, need 4 boards | ** - HV distribution boards: has not yet been designed, need 4 boards | ||
** - LV cables: missing about 20 cables, waiting for the last delivery batch. | ** - LV cables: missing about 20 cables, waiting for the last delivery batch. | ||
− | ** - LV distribution boards [https://halldweb.jlab.org/detectors/fcal2/cables/lv_distribution/lv_dist_board.jpg ]. One board out of 4 is ready, using for testing dividers [[ | + | ** - LV distribution boards [https://halldweb.jlab.org/detectors/fcal2/cables/lv_distribution/lv_dist_board.jpg ]. One board out of 4 is ready, using for testing dividers [[File:lv_distribution.jpg} test]] |
** - LED: prototype board is ready, have to start testing | ** - LED: prototype board is ready, have to start testing | ||
* '''Ongoing projects''' - All | * '''Ongoing projects''' - All |
Revision as of 22:50, 23 May 2024
Meeting time and location:
- 9:30 am EST (JLab time) remote only
- Connection information
Agenda
- Preparation of parts for ECAL -- Sasha
- - HV long cable, 18 ready (out of 36), discussion with the DSG group regarding help
- - HV distribution boards: has not yet been designed, need 4 boards
- - LV cables: missing about 20 cables, waiting for the last delivery batch.
- - LV distribution boards [1]. One board out of 4 is ready, using for testing dividers [[File:lv_distribution.jpg} test]]
- - LED: prototype board is ready, have to start testing
- Ongoing projects - All
- Testing of PMT dividers -- Sasha / Vlad / George / Mindy
- - File:Regulators.xlsx Map of dividers with removed regulators
- - Testing procedure [2]
- - All dividers have been fabricated and tested by George [3]
- Continue removing regulators from the PCB (about 70 regulators have been removed, require re-testing dividers)
- Installation of the FCAL2 detector & integration to GlueX -- Sasha / Vlad / Hakob / Laveen
- Installation and testing cables and dividers [4] [5]
- Detector installation page
- Summer students -- Sasha
- - Olivia, Ben, and Shane are on site. Expect one student from Wuhan (have to start with the paperwork)
- - Projects: document all test results, assist with the cable/divider installation, install signal cables on patch panel, work on the ECAL monitoring plots
- Beam tests with the PS
- measure shower beam profile and reconstruction in the crystal/LG transition region
- (install prototype with 5x5 PbWO4 modules + ? LG)
- Other hardware projects
- prototype of the ECAL veto counter (?)
- FCAL2 posters for open house
- JEF/ECAL/FCAL poster (Laveen + students + feedback from all of us)
- JEF physics poster (Laveen)