+ | =Minutes= | ||
+ | Attendees: Bill, Sasha, Arshak, Liping, Jane, Phil, Vlad, Stjepan, Olga | ||
+ | * Temporary safety documents in new ePas system in place so work on FCAL-2 installation could proceed | ||
+ | * Received one more batch of short HV cables, expect 2 more batches | ||
+ | * LV cables have not been delivered yet (although we received the first articles last year) | ||
+ | * LV distribution boards arrived and checked | ||
+ | * Plexiglas installation for lead glass finished last week, so installation of LMS for insert can start | ||
+ | ** Feed LMS bundles through hole, to interface with integrating sphere to be mounted on optical bench | ||
+ | * 637 PMT dividers tested, waiting for the remaining to be fabricated | ||
+ | * HV cables being routed through chains | ||
+ | * Still no power on ECAL platform | ||
+ | * Short on manpower: detector support group can help with divider testing | ||
+ | * Igal continues to work with Daniel L. on machine learning algorithms to suppress background |
Latest revision as of 09:32, 22 January 2024
Meeting time and location:
- 9:30 am EST (JLab time) remote only
- Connection information
Agenda
- Preparation of parts for ECAL -- Sasha
- - signal cables - done
- - signal patch panel [1] - done
- - HV cables: received 165 short cables during this week (1280 in total)
- - HV distribution boards: in preparation
- - LV cables: received first article of short cables, production started on Dec. 7, have not received yet.
- - LV distribution boards. Received 4 boards, performed initial cehck, need to solder connectors
- - Optical fibers and parts for the trigger/DAQ have been ordered
- Ongoing projects -- Sasha, all
- - Testing and labeling cables [2], 120 short HV cables testes and labeled during this week.
- - Prepare modules for the TAC and prototypes (using crystals with some imperfections)
- - Preparation of the LMS
- - Need to glue Al flange to the optical fiber
- - Ready for installation [5]
- - Radiation tests of the PMT active base [6]
- Finished tests, working on the tech note
- - Inventory database and GUI for installed electronics
- - Summer Students (2023)
- Testing of PMT dividers -- Sasha / Vlad / Aoran
- Installation of the FCAL2 detector & integration to GlueX -- Sasha / Vlad / Hakob
- Detector installation [9][10][11]
- Installation of the LMS
- Cable and divider installation
- Started yesterday, making a decision how to stretch them [14]
- Still no power on the ECAL platform (expect delay with the development of the trigger/DAQ)
- Detector installation page
Minutes
Attendees: Bill, Sasha, Arshak, Liping, Jane, Phil, Vlad, Stjepan, Olga
- Temporary safety documents in new ePas system in place so work on FCAL-2 installation could proceed
- Received one more batch of short HV cables, expect 2 more batches
- LV cables have not been delivered yet (although we received the first articles last year)
- LV distribution boards arrived and checked
- Plexiglas installation for lead glass finished last week, so installation of LMS for insert can start
- Feed LMS bundles through hole, to interface with integrating sphere to be mounted on optical bench
- 637 PMT dividers tested, waiting for the remaining to be fabricated
- HV cables being routed through chains
- Still no power on ECAL platform
- Short on manpower: detector support group can help with divider testing
- Igal continues to work with Daniel L. on machine learning algorithms to suppress background