Difference between revisions of "JEF meeting, August 25, 2023"
From GlueXWiki
(→Agenda) |
(→Agenda) |
||
Line 24: | Line 24: | ||
** Cutting optical fibers and gluing plastic caps [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/06_23_2023/glue_caps.jpg], waiting for 7600 ft of optical fibers | ** Cutting optical fibers and gluing plastic caps [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/06_23_2023/glue_caps.jpg], waiting for 7600 ft of optical fibers | ||
** Work on refurbishing LG modules. About 80 modules have small imperfections and have to be fixed (rejected during installation) | ** Work on refurbishing LG modules. About 80 modules have small imperfections and have to be fixed (rejected during installation) | ||
− | ** | + | **:- Mindy is re-wrapping crystals (12 during last week). She also continues soldering wires to the PMT connectors |
** [https://docs.google.com/presentation/d/1euIA49SszoQmSM4Lxu1OtZ8OfjltgwzXIbXo6TPEB3s/edit#slide=id.p Report from students] | ** [https://docs.google.com/presentation/d/1euIA49SszoQmSM4Lxu1OtZ8OfjltgwzXIbXo6TPEB3s/edit#slide=id.p Report from students] | ||
* '''[[Testing of PMT dividers]]''' -- Sasha / Vlad | * '''[[Testing of PMT dividers]]''' -- Sasha / Vlad |
Revision as of 08:49, 25 August 2023
Meeting time and location:
- 9:30 am EST (JLab time) remote only
- Connection information
Agenda
- Preparation of parts for ECAL modules -- Sasha
- Crystals:
- Received 1100 short signal cables [3]
- Procurement parts for the LMS:
- - Waiting for 7,600 ft of optical fibers (August/September)
- Module fabrication -- Sasha
- All modules have been fabricated, checked, and inventorized (about 1610 modules in total)
- Ongoing projects -- Sasha, all
- Visual inspections of fabricated modules [4] - done
- All crystals moved to Hall D[5] [6][7].
- Tested, labeled, and bundled all 100 (+ 2 spares) [8] signal cables connected from the flash ADC to the patch panel [9] - done
- Test and label 1100 short signal cables - ongoing
- Tested fabricated modules using LMS [10] - done (need to update the wiki page)
- Cutting optical fibers and gluing plastic caps [11], waiting for 7600 ft of optical fibers
- Work on refurbishing LG modules. About 80 modules have small imperfections and have to be fixed (rejected during installation)
- - Mindy is re-wrapping crystals (12 during last week). She also continues soldering wires to the PMT connectors
- Report from students
- Testing of PMT dividers -- Sasha / Vlad
- Received 10 dividers (first article) ! , going to test them during this week (Chris)
- Proceedures
- Installation of the FCAL2 detector & integration to GlueX -- Sasha / Arshak / Vlad / Hakob
- Detector installation [12][13][14]
- Detector installation page
- Updates from the meetings with Tim's group [15]
- Discussion of the FCAL2 installation procedures [16]
- Final mapping of low-voltage cables
- Mindy continues with wrapping crystals and soldering wires to sockets.
- Projects for summer students
- Summer Students (2023)
- Light monitoring system -- Arshak