Difference between revisions of "JEF meeting, June 23, 2023"
From GlueXWiki
(Created page with "Meeting time and location: *9:30 am EST (JLab time) remote only * [https://halldweb.jlab.org/wiki-private/index.php/JEF_Weekly_Meeting#Connection_information Connection inform...") |
(→Agenda) |
||
Line 3: | Line 3: | ||
* [https://halldweb.jlab.org/wiki-private/index.php/JEF_Weekly_Meeting#Connection_information Connection information] | * [https://halldweb.jlab.org/wiki-private/index.php/JEF_Weekly_Meeting#Connection_information Connection information] | ||
+ | |||
+ | =Agenda= | ||
+ | |||
+ | *'''Preparation of parts for ECAL modules''' -- Sasha | ||
+ | ** Crystals: | ||
+ | **: - <span style="color:#FF0000"> Received all crystals from CRYTUR [https://halldweb.jlab.org/wiki/index.php/CRYTUR ]. </span> | ||
+ | **: - Available for wrapping: 35 CRYTUR | ||
+ | ** Received 1000 long signal cables | ||
+ | ** Procurement parts for the LMS: | ||
+ | **: - 16,400 ft of optical fibers delivered to the lab. 7,600 will be delivered in September. | ||
+ | **: - Expect to receive all plastic caps for the LMS today (can start gluing them to fibers during next week) | ||
+ | **: - Cutting Tedlar foils, wrapping PMT light guides, etc. | ||
+ | ** PO submitted for PMT dividers (expect to receive the first batch in the end of June) | ||
+ | * '''Module fabrication''' -- Sasha | ||
+ | <!-- ** [https://halldweb.jlab.org/detectors/fcal2/module_fabrication/status/fcal_fabrication.pdf Status of fabrication ] --> | ||
+ | ** Fabricated modules: <span style="color:#FF0000"> Total 1572 </span> (remaining 24 + spares) | ||
+ | **: - 10 modules fabricated during last week <!-- [[File:Fab_mod_may_2023.jpg]] --> | ||
+ | ** [https://docs.google.com/presentation/d/1euIA49SszoQmSM4Lxu1OtZ8OfjltgwzXIbXo6TPEB3s/edit#slide=id.p Report from students] | ||
+ | * '''Ongoing projects''' -- Sasha, all | ||
+ | ** Visual inspections of fabricated modules [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/19_05_2023/modules_qa.docx] | ||
+ | **: -1357 modules have been checked (572 SICCAS + 785 CRYTUR) [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/19_05_2023/modules_shelves.jpg] | ||
+ | ** Testing and labeling signal cables (connect flash ADC with the detector distribution panel) [https://halldweb.jlab.org/wiki/index.php/Testing_and_labeling_cables] | ||
+ | **: - 725 long signal cables have been tested [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/25_05_2023/boxes_with_labels.jpg] | ||
+ | **: - [https://halldweb.jlab.org/wiki/index.php/Testing_labeling_cables Cable tester and label maker] | ||
+ | **: - 12 bundles of signal cables are ready (out of 100) | ||
+ | ** Removing signal cables from the FCAL [https://halldweb.jlab.org/wiki/index.php/Removing_FCAL_cables_from_the_detector] | ||
+ | * '''[[Testing of PMT dividers]]''' -- Sasha / Vlad | ||
+ | ** All dividers have been ordered (by Chris S.) | ||
+ | ** Preparing setups for testing modules and dividers | ||
+ | * '''[https://halldweb.jlab.org/wiki/index.php/FCAL_Insert_Module_Fabrication Proceedures]''' | ||
+ | * '''Installation of the FCAL2 detector & integration to GlueX''' -- Sasha / Arshak | ||
+ | ** [https://halldweb.jlab.org/wiki/index.php/FCAL_Installation Detector installation page] | ||
+ | ** Updates from the meetings with Tim's group [https://halldweb.jlab.org/wiki/index.php/FCAL_2_Design_Meetings] | ||
+ | ** Discussion of the FCAL2 installation procedures [https://halldweb.jlab.org/wiki/index.php/FCAL_2_Installation_Meetings] | ||
+ | ** [https://halldweb.jlab.org/wiki/index.php/Distribution_of_signals_and_voltages Final mapping of low-voltage cables] | ||
+ | ** Manpower and division of tasks | ||
+ | ** [https://halldweb.jlab.org/wiki/index.php/List_of_tasks_and_manpower Projects for summer students] | ||
+ | ** [https://halldweb.jlab.org/detectors/fcal2/installation/students_2023/list_of_students_2023.xlsx Summer Students (2023) ] | ||
+ | <!-- ** [https://halldweb.jlab.org/detectors/fcal2/installation/photos Disassembling FCAL] --> | ||
+ | *'''Light monitoring system''' -- Arshak | ||
+ | **Fiber polisher [https://userweb.jlab.org/~aasatury/Fcal_LMS/IMG_20230605_174857.jpg] | ||
+ | ** [https://userweb.jlab.org/~aasatury/Fcal_LMS/fiber_prep/IMG_20230616_090218.jpg ~450 fibers were cut and half of them are already glued to donates] | ||
+ | ** [https://userweb.jlab.org/~aasatury/Fcal_LMS/fiber_prep/IMG_20230616_090332.jpg Glued fibers] | ||
+ | * '''Simulations/Analysis''' | ||
=Agenda= | =Agenda= |
Revision as of 22:42, 22 June 2023
Meeting time and location:
- 9:30 am EST (JLab time) remote only
- Connection information
Agenda
- Preparation of parts for ECAL modules -- Sasha
- Crystals:
- - Received all crystals from CRYTUR [1].
- - Available for wrapping: 35 CRYTUR
- Received 1000 long signal cables
- Procurement parts for the LMS:
- - 16,400 ft of optical fibers delivered to the lab. 7,600 will be delivered in September.
- - Expect to receive all plastic caps for the LMS today (can start gluing them to fibers during next week)
- - Cutting Tedlar foils, wrapping PMT light guides, etc.
- PO submitted for PMT dividers (expect to receive the first batch in the end of June)
- Crystals:
- Module fabrication -- Sasha
- Fabricated modules: Total 1572 (remaining 24 + spares)
- - 10 modules fabricated during last week
- Report from students
- Fabricated modules: Total 1572 (remaining 24 + spares)
- Ongoing projects -- Sasha, all
- Visual inspections of fabricated modules [2]
- -1357 modules have been checked (572 SICCAS + 785 CRYTUR) [3]
- Testing and labeling signal cables (connect flash ADC with the detector distribution panel) [4]
- - 725 long signal cables have been tested [5]
- - Cable tester and label maker
- - 12 bundles of signal cables are ready (out of 100)
- Removing signal cables from the FCAL [6]
- Visual inspections of fabricated modules [2]
- Testing of PMT dividers -- Sasha / Vlad
- All dividers have been ordered (by Chris S.)
- Preparing setups for testing modules and dividers
- Proceedures
- Installation of the FCAL2 detector & integration to GlueX -- Sasha / Arshak
- Detector installation page
- Updates from the meetings with Tim's group [7]
- Discussion of the FCAL2 installation procedures [8]
- Final mapping of low-voltage cables
- Manpower and division of tasks
- Projects for summer students
- Summer Students (2023)
- Light monitoring system -- Arshak
- Simulations/Analysis
Agenda
- Preparation of parts for ECAL modules -- Sasha
- Module fabrication -- Sasha
- Ongoing projects -- Sasha, all
- Testing of PMT dividers -- Sasha / Vlad
- Procedures
- Installation of the FCAL2 detector & integration to GlueX -- Sasha / Arshak
- Light monitoring system -- Arshak