Difference between revisions of "JEF meeting, June 2, 2023"
From GlueXWiki
Line 24: | Line 24: | ||
** [https://halldweb.jlab.org/wiki/index.php/Testing_labeling_cables Cable tester and label maker] | ** [https://halldweb.jlab.org/wiki/index.php/Testing_labeling_cables Cable tester and label maker] | ||
**: - 600 long signal cables have been tested [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/25_05_2023/boxes_with_labels.jpg] | **: - 600 long signal cables have been tested [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/25_05_2023/boxes_with_labels.jpg] | ||
+ | |||
+ | * '''Removing signal cables from the FCAL''' [https://halldweb.jlab.org/wiki/index.php/Removing_FCAL_cables_from_the_detector] | ||
* '''[[Testing of PMT dividers]]''' -- Sasha / Vlad | * '''[[Testing of PMT dividers]]''' -- Sasha / Vlad | ||
** Most parts for the active base have been arrived to the lab (including PCBs) | ** Most parts for the active base have been arrived to the lab (including PCBs) |
Revision as of 08:59, 2 June 2023
Meeting time and location:
- 9:30 am EST (JLab time) remote only
- Connection information
Agenda
Preparation of parts for ECAL modules -- Sasha
- Crystals:
- Received 50 crystals from CRYTUR [1]. Remaining 45 crystals are expected to be delivered to the Lab in May/June.
- Wrapped crystals during last week: 16
- Available for wrapping: 10 CRYTUR
- Received 725 long signal cables
- Procurement parts for the LMS:
- 16,400 ft of optical fibers delivered to the lab. 7,600 will be delivered in September.
- Expect to receive all plastic caps for the LMS during next week
- Crystals:
- Module fabrication -- Sasha
- Fabricated modules: Total 1558
- 16 modules fabricated during last week
- Report from students
- Fabricated modules: Total 1558
- Visual inspections of fabricated modules [2]
- -715 modules have been checked (273 SICCAS + 442 CRYTUR) [3]
- Testing and labeling cables
- Cable tester and label maker
- - 600 long signal cables have been tested [4]
- Cable tester and label maker
- Removing signal cables from the FCAL [5]
- Testing of PMT dividers -- Sasha / Vlad
- Most parts for the active base have been arrived to the lab (including PCBs)
- All dividers will be ordered during next week (by Chris S.)
- Installation of the FCAL2 detector & integration to GlueX -- Sasha / Arshak
- Detector installation page
- Updates from the meetings with Tim's group [6]
- Discussion of the FCAL2 installation procedures [7]
- Final mapping of low-voltage cables
- Manpower and division of tasks
- Projects for summer students
- Summer Students (2023)
- Light monitoring system -- Arshak
- Simulations/Analysis