* '''Visual inspections of fabricated modules [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/19_05_2023/modules_qa.docx] ''' | * '''Visual inspections of fabricated modules [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/19_05_2023/modules_qa.docx] ''' | ||
**: 715 modules have been checked (273 SICCAS + 442 CRYTUR) [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/19_05_2023/modules_shelves.jpg] | **: 715 modules have been checked (273 SICCAS + 442 CRYTUR) [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/19_05_2023/modules_shelves.jpg] | ||
− | * '''[[Testing of PMT dividers]]''' -- Sasha / Vlad | + | * '''[[Testing of PMT dividers]]''' -- Sasha / Vlad |
− | ** | + | ** Most parts for the active base have been arrived to the lab (including PCBs) |
− | ** | + | ** All dividers will be ordered during next week |
* '''Installation of the FCAL2 detector & integration to GlueX''' -- Sasha / Arshak | * '''Installation of the FCAL2 detector & integration to GlueX''' -- Sasha / Arshak | ||
** [https://halldweb.jlab.org/wiki/index.php/FCAL_Installation Detector installation page] | ** [https://halldweb.jlab.org/wiki/index.php/FCAL_Installation Detector installation page] |
Revision as of 17:39, 25 May 2023
eeting time and location:
- 9:30 am EST (JLab time) remote only
- Connection information
Agenda
- Preparation of parts for FCAL2 modules -- Sasha
- Crystals:
- Received 50 crystals from CRYTUR [1], 10 have been recently sent out. Remaining 45 crystals.
- Wrapped crystals: 10
- Available for wrapping: 10 CRYTUR
- Received 725 long signal cables
- Procurement parts for the LMS:
- 16,400 ft of optical fibers delivered to the lab. 7,600 will be delivered in September.
- Expect to receive all plastic caps for the LMS during next week
- Crystals:
- Module fabrication -- Sasha
- Fabricated modules: Total 1558
- 16 modules fabricated during last week
- Report from students
- Fabricated modules: Total 1558
- Visual inspections of fabricated modules [2]
- 715 modules have been checked (273 SICCAS + 442 CRYTUR) [3]
- Testing of PMT dividers -- Sasha / Vlad
- Most parts for the active base have been arrived to the lab (including PCBs)
- All dividers will be ordered during next week
- Installation of the FCAL2 detector & integration to GlueX -- Sasha / Arshak
- Detector installation page
- Updates from the meetings with Tim's group [4]
- Discussion of the FCAL2 installation procedures [5]
- Final mapping of low-voltage cables
- Manpower and division of tasks
- Projects for summer students
- Summer Students (2023)
- Light monitoring system -- Arshak
- Simulations/Analysis