Difference between revisions of "JEF meeting, June 9, 2023"
From GlueXWiki
(→Agenda) |
(→Agenda) |
||
(14 intermediate revisions by one other user not shown) | |||
Line 5: | Line 5: | ||
=Agenda= | =Agenda= | ||
− | '''Preparation of parts for ECAL modules''' -- Sasha | + | *'''Preparation of parts for ECAL modules''' -- Sasha |
** Crystals: | ** Crystals: | ||
− | **: Received all crystals from CRYTUR [https://halldweb.jlab.org/wiki/index.php/CRYTUR ]. | + | **: - <span style="color:#FF0000"> Received all crystals from CRYTUR [https://halldweb.jlab.org/wiki/index.php/CRYTUR ]. </span> |
− | **: Available for wrapping: 35 CRYTUR | + | **: - Available for wrapping: 35 CRYTUR |
** Received 1000 long signal cables | ** Received 1000 long signal cables | ||
** Procurement parts for the LMS: | ** Procurement parts for the LMS: | ||
− | **: 16,400 ft of optical fibers delivered to the lab. 7,600 will be delivered in September. | + | **: - 16,400 ft of optical fibers delivered to the lab. 7,600 will be delivered in September. |
− | **: Expect to receive all plastic caps for the LMS today (can start gluing them to fibers during next week) | + | **: - Expect to receive all plastic caps for the LMS today (can start gluing them to fibers during next week) |
− | ** PO submitted for PMT dividers (expect to receive the first batch in the end of June) | + | **: - Cutting Tedlar foils, wrapping PMT light guides, etc. |
+ | ** PO submitted for PMT dividers (expect to receive the first batch in the end of June) | ||
* '''Module fabrication''' -- Sasha | * '''Module fabrication''' -- Sasha | ||
<!-- ** [https://halldweb.jlab.org/detectors/fcal2/module_fabrication/status/fcal_fabrication.pdf Status of fabrication ] --> | <!-- ** [https://halldweb.jlab.org/detectors/fcal2/module_fabrication/status/fcal_fabrication.pdf Status of fabrication ] --> | ||
** Fabricated modules: <span style="color:#FF0000"> Total 1572 </span> (remaining 24 + spares) | ** Fabricated modules: <span style="color:#FF0000"> Total 1572 </span> (remaining 24 + spares) | ||
− | **: 10 modules fabricated during last week <!-- [[File:Fab_mod_may_2023.jpg]] --> | + | **: - 10 modules fabricated during last week <!-- [[File:Fab_mod_may_2023.jpg]] --> |
** [https://docs.google.com/presentation/d/1euIA49SszoQmSM4Lxu1OtZ8OfjltgwzXIbXo6TPEB3s/edit#slide=id.p Report from students] | ** [https://docs.google.com/presentation/d/1euIA49SszoQmSM4Lxu1OtZ8OfjltgwzXIbXo6TPEB3s/edit#slide=id.p Report from students] | ||
− | * '''Visual inspections of fabricated modules [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/19_05_2023/modules_qa.docx] | + | * '''Ongoing projects''' -- Sasha, all |
− | *: -1357 modules have been checked (572 SICCAS + 785 CRYTUR) [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/19_05_2023/modules_shelves.jpg] | + | ** Visual inspections of fabricated modules [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/19_05_2023/modules_qa.docx] |
− | * | + | **: -1357 modules have been checked (572 SICCAS + 785 CRYTUR) [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/19_05_2023/modules_shelves.jpg] |
− | + | ** Testing and labeling signal cables (connect flash ADC with the detector distribution panel) [https://halldweb.jlab.org/wiki/index.php/Testing_and_labeling_cables] | |
− | **: - | + | **: - 725 long signal cables have been tested [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/25_05_2023/boxes_with_labels.jpg] |
− | * | + | **: - [https://halldweb.jlab.org/wiki/index.php/Testing_labeling_cables Cable tester and label maker] |
+ | **: - 12 bundles of signal cables are ready (out of 100) | ||
+ | ** Removing signal cables from the FCAL [https://halldweb.jlab.org/wiki/index.php/Removing_FCAL_cables_from_the_detector] | ||
* '''[[Testing of PMT dividers]]''' -- Sasha / Vlad | * '''[[Testing of PMT dividers]]''' -- Sasha / Vlad | ||
− | ** | + | ** All dividers have been ordered (by Chris S.) |
− | + | ** Preparing setups for testing modules and dividers | |
* '''[https://halldweb.jlab.org/wiki/index.php/FCAL_Insert_Module_Fabrication Proceedures]''' | * '''[https://halldweb.jlab.org/wiki/index.php/FCAL_Insert_Module_Fabrication Proceedures]''' | ||
* '''Installation of the FCAL2 detector & integration to GlueX''' -- Sasha / Arshak | * '''Installation of the FCAL2 detector & integration to GlueX''' -- Sasha / Arshak | ||
** [https://halldweb.jlab.org/wiki/index.php/FCAL_Installation Detector installation page] | ** [https://halldweb.jlab.org/wiki/index.php/FCAL_Installation Detector installation page] | ||
** Updates from the meetings with Tim's group [https://halldweb.jlab.org/wiki/index.php/FCAL_2_Design_Meetings] | ** Updates from the meetings with Tim's group [https://halldweb.jlab.org/wiki/index.php/FCAL_2_Design_Meetings] | ||
− | + | ** Discussion of the FCAL2 installation procedures [https://halldweb.jlab.org/wiki/index.php/FCAL_2_Installation_Meetings] | |
** [https://halldweb.jlab.org/wiki/index.php/Distribution_of_signals_and_voltages Final mapping of low-voltage cables] | ** [https://halldweb.jlab.org/wiki/index.php/Distribution_of_signals_and_voltages Final mapping of low-voltage cables] | ||
** Manpower and division of tasks | ** Manpower and division of tasks | ||
Line 39: | Line 42: | ||
<!-- ** [https://halldweb.jlab.org/detectors/fcal2/installation/photos Disassembling FCAL] --> | <!-- ** [https://halldweb.jlab.org/detectors/fcal2/installation/photos Disassembling FCAL] --> | ||
*'''Light monitoring system''' -- Arshak | *'''Light monitoring system''' -- Arshak | ||
− | + | **Fiber polisher [https://userweb.jlab.org/~aasatury/Fcal_LMS/IMG_20230605_174857.jpg] | |
* '''Simulations/Analysis''' | * '''Simulations/Analysis''' | ||
* [https://halldweb.jlab.org/doc-private/DocDB/ShowDocument?docid=6092 Talk at ECT* workshop next week] -- Simon | * [https://halldweb.jlab.org/doc-private/DocDB/ShowDocument?docid=6092 Talk at ECT* workshop next week] -- Simon |
Latest revision as of 09:39, 9 June 2023
Meeting time and location:
- 9:30 am EST (JLab time) remote only
- Connection information
Agenda
- Preparation of parts for ECAL modules -- Sasha
- Crystals:
- - Received all crystals from CRYTUR [1].
- - Available for wrapping: 35 CRYTUR
- Received 1000 long signal cables
- Procurement parts for the LMS:
- - 16,400 ft of optical fibers delivered to the lab. 7,600 will be delivered in September.
- - Expect to receive all plastic caps for the LMS today (can start gluing them to fibers during next week)
- - Cutting Tedlar foils, wrapping PMT light guides, etc.
- PO submitted for PMT dividers (expect to receive the first batch in the end of June)
- Crystals:
- Module fabrication -- Sasha
- Fabricated modules: Total 1572 (remaining 24 + spares)
- - 10 modules fabricated during last week
- Report from students
- Fabricated modules: Total 1572 (remaining 24 + spares)
- Ongoing projects -- Sasha, all
- Visual inspections of fabricated modules [2]
- -1357 modules have been checked (572 SICCAS + 785 CRYTUR) [3]
- Testing and labeling signal cables (connect flash ADC with the detector distribution panel) [4]
- - 725 long signal cables have been tested [5]
- - Cable tester and label maker
- - 12 bundles of signal cables are ready (out of 100)
- Removing signal cables from the FCAL [6]
- Visual inspections of fabricated modules [2]
- Testing of PMT dividers -- Sasha / Vlad
- All dividers have been ordered (by Chris S.)
- Preparing setups for testing modules and dividers
- Proceedures
- Installation of the FCAL2 detector & integration to GlueX -- Sasha / Arshak
- Detector installation page
- Updates from the meetings with Tim's group [7]
- Discussion of the FCAL2 installation procedures [8]
- Final mapping of low-voltage cables
- Manpower and division of tasks
- Projects for summer students
- Summer Students (2023)
- Light monitoring system -- Arshak
- Fiber polisher [9]
- Simulations/Analysis
- Talk at ECT* workshop next week -- Simon