Difference between revisions of "JEF meeting, July 26, 2024"
From GlueXWiki
(→Agenda) |
(→Agenda) |
||
Line 5: | Line 5: | ||
=Agenda= | =Agenda= | ||
*'''Preparation of parts for ECAL''' -- Sasha | *'''Preparation of parts for ECAL''' -- Sasha | ||
− | ** - HV long cable | + | ** - HV long cable: Sammy and Mindy have to assemble 10 cables |
− | ** - HV distribution boards | + | ** - HV distribution boards. Chris has completed the design of the HV distribution boards. We met with Chris, Tim, and Scot regarding location of the boards on the detector frame |
− | ** - LED: prototype | + | ** - LED: Started testing the prototype of the LMS (need to make the detector room light tight) |
* '''Ongoing projects''' - All | * '''Ongoing projects''' - All | ||
<!-- ** - [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/05_10_2024/May-10-2024-L.pdf Update from Laveen] --> | <!-- ** - [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/05_10_2024/May-10-2024-L.pdf Update from Laveen] --> |
Revision as of 09:17, 26 July 2024
Meeting time and location:
- 9:30 am EST (JLab time) remote only
- Connection information
Agenda
- Preparation of parts for ECAL -- Sasha
- - HV long cable: Sammy and Mindy have to assemble 10 cables
- - HV distribution boards. Chris has completed the design of the HV distribution boards. We met with Chris, Tim, and Scot regarding location of the boards on the detector frame
- - LED: Started testing the prototype of the LMS (need to make the detector room light tight)
- Ongoing projects - All
- Testing of PMT dividers -- Sasha / Vlad / George / Mindy
- - File:Regulators.xlsx Map of dividers with removed regulators
- - Testing procedure [1]
- - All dividers have been fabricated and tested by George [2]
- Continue removing regulators from the PCB (about 70 regulators have been removed, require re-testing dividers)
- Installation of the FCAL2 detector & integration to GlueX -- Sasha / Vlad / Hakob / Laveen
- Report from students [3]
- Installation and testing cables and dividers [4][5]
- Installation of long signal cables [6]
- Installing LV patch panels and cables [7]
- Installation of optical fibers [8]
- Detector installation page
- Safety briefings
- Summer students -- Sasha
- - Olivia, Ben, and Shane are on site. Expect one student from Wuhan (have to start with the paperwork)
- - Projects: document all test results, assist with the cable/divider installation, install signal cables on patch panel, work on the ECAL monitoring plots
- Beam tests with the PS
- measure shower beam profile and reconstruction in the crystal/LG transition region
- (install prototype with 5x5 PbWO4 modules + ? LG)
- Other hardware projects
- prototype of the ECAL veto counter (?)
- Analysis/Simulation