Difference between revisions of "JEF meeting, July 26, 2024"
From GlueXWiki
(Created page with "Meeting time and location: *9:30 am EST (JLab time) remote only * [https://halldweb.jlab.org/wiki-private/index.php/JEF_Weekly_Meeting#Connection_information Connection inform...") |
(→Agenda) |
||
Line 5: | Line 5: | ||
=Agenda= | =Agenda= | ||
*'''Preparation of parts for ECAL''' -- Sasha | *'''Preparation of parts for ECAL''' -- Sasha | ||
+ | ** - HV long cable, 25 ready (out of 36), discussion with the DSG group regarding help (Sammy and Mindy) | ||
+ | ** - HV distribution boards: has not yet been designed, need 4 boards (meeting with Scot/Tim regarding installation during next week) | ||
+ | ** - LED: prototype board is ready, have to start testing | ||
* '''Ongoing projects''' - All | * '''Ongoing projects''' - All | ||
+ | <!-- ** - [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/05_10_2024/May-10-2024-L.pdf Update from Laveen] --> | ||
* '''[[Testing of PMT dividers]]''' -- Sasha / Vlad / George / Mindy | * '''[[Testing of PMT dividers]]''' -- Sasha / Vlad / George / Mindy | ||
+ | ** - [[File:regulators.xlsx]] Map of dividers with removed regulators | ||
+ | ** - Testing procedure [https://halldweb.jlab.org/detectors/fcal2/dividers/divider_test_guide.pptx] | ||
+ | ** - All dividers have been fabricated and tested by George [https://halldweb.jlab.org/wiki/index.php/Final_test_of_dividers] | ||
+ | *** Continue removing regulators from the PCB (about 70 regulators have been removed, require re-testing dividers) | ||
* '''Installation of the FCAL2 detector & integration to GlueX''' -- Sasha / Vlad / Hakob / Laveen | * '''Installation of the FCAL2 detector & integration to GlueX''' -- Sasha / Vlad / Hakob / Laveen | ||
+ | ** Report from students [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/06_28_2024/student_report_06_28_2024.pptx] | ||
+ | ** Installation and testing cables and dividers [https://logbooks.jlab.org/entry/4310168][https://logbooks.jlab.org/entry/4312779] | ||
+ | ** Installation of long signal cables [https://logbooks.jlab.org/entry/4312667] | ||
+ | ** Installing LV patch panels and cables [https://logbooks.jlab.org/entry/4312759] | ||
+ | ** Installation of optical fibers [https://logbooks.jlab.org/entry/4311499] | ||
+ | ** [https://halldweb.jlab.org/wiki/index.php/FCAL_Installation Detector installation page] | ||
+ | ** [https://halldweb.jlab.org/detectors/fcal2/installation/safety_docs/Document_240716_195013-1.pdf Safety briefings] | ||
* '''Summer students''' -- Sasha | * '''Summer students''' -- Sasha | ||
+ | ** - Olivia, Ben, and Shane are on site. Expect one student from Wuhan (have to start with the paperwork) | ||
+ | ** - Projects: document all test results, assist with the cable/divider installation, install signal cables on patch panel, work on the ECAL monitoring plots | ||
* '''Beam tests with the PS''' | * '''Beam tests with the PS''' | ||
+ | *** measure shower beam profile and reconstruction in the crystal/LG transition region | ||
+ | *** (install prototype with 5x5 PbWO4 modules + ? LG) | ||
* '''Other hardware projects''' | * '''Other hardware projects''' | ||
+ | ** prototype of the ECAL veto counter (?) | ||
*'''Analysis/Simulation''' | *'''Analysis/Simulation''' |
Revision as of 09:13, 26 July 2024
Meeting time and location:
- 9:30 am EST (JLab time) remote only
- Connection information
Agenda
- Preparation of parts for ECAL -- Sasha
- - HV long cable, 25 ready (out of 36), discussion with the DSG group regarding help (Sammy and Mindy)
- - HV distribution boards: has not yet been designed, need 4 boards (meeting with Scot/Tim regarding installation during next week)
- - LED: prototype board is ready, have to start testing
- Ongoing projects - All
- Testing of PMT dividers -- Sasha / Vlad / George / Mindy
- - File:Regulators.xlsx Map of dividers with removed regulators
- - Testing procedure [1]
- - All dividers have been fabricated and tested by George [2]
- Continue removing regulators from the PCB (about 70 regulators have been removed, require re-testing dividers)
- Installation of the FCAL2 detector & integration to GlueX -- Sasha / Vlad / Hakob / Laveen
- Report from students [3]
- Installation and testing cables and dividers [4][5]
- Installation of long signal cables [6]
- Installing LV patch panels and cables [7]
- Installation of optical fibers [8]
- Detector installation page
- Safety briefings
- Summer students -- Sasha
- - Olivia, Ben, and Shane are on site. Expect one student from Wuhan (have to start with the paperwork)
- - Projects: document all test results, assist with the cable/divider installation, install signal cables on patch panel, work on the ECAL monitoring plots
- Beam tests with the PS
- measure shower beam profile and reconstruction in the crystal/LG transition region
- (install prototype with 5x5 PbWO4 modules + ? LG)
- Other hardware projects
- prototype of the ECAL veto counter (?)
- Analysis/Simulation