Line 27: | Line 27: | ||
* '''Other hardware projects''' | * '''Other hardware projects''' | ||
** prototype of the ECAL veto counter (?) | ** prototype of the ECAL veto counter (?) | ||
+ | *** Impact of veto on eta channels from Feb'24 collaboration meeting: [[File:p9.pdf]] | ||
*'''FCAL2 posters for open house''' | *'''FCAL2 posters for open house''' | ||
** JEF/ECAL/FCAL poster (Laveen + students + feedback from all of us) | ** JEF/ECAL/FCAL poster (Laveen + students + feedback from all of us) | ||
** [https://halldweb.jlab.org/wiki/images/2/2c/1-OH24Poster-V-LAVEEN-revised.pdf JEF physics poster] (Laveen) | ** [https://halldweb.jlab.org/wiki/images/2/2c/1-OH24Poster-V-LAVEEN-revised.pdf JEF physics poster] (Laveen) | ||
*'''Analysis/Simulation''' | *'''Analysis/Simulation''' |
Revision as of 08:16, 24 May 2024
Meeting time and location:
- 9:30 am EST (JLab time) remote only
- Connection information
Agenda
- Preparation of parts for ECAL -- Sasha
- - HV long cable, 18 ready (out of 36), discussion with the DSG group regarding help
- - HV distribution boards: has not yet been designed, need 4 boards
- - LV cables: missing about 20 cables, waiting for the last delivery batch.
- - LV distribution boards [1]. One board out of 4 is ready, using for testing dividers Media:lv_distribution.jpg
- - LED: prototype board is ready, have to start testing
- Ongoing projects - All
- Testing of PMT dividers -- Sasha / Vlad / George / Mindy
- - File:Regulators.xlsx Map of dividers with removed regulators
- - Testing procedure [2]
- - All dividers have been fabricated and tested by George [3]
- Continue removing regulators from the PCB (about 70 regulators have been removed, require re-testing dividers)
- Installation of the FCAL2 detector & integration to GlueX -- Sasha / Vlad / Hakob / Laveen
- Installation and testing cables and dividers [4] [5]
- Detector installation page
- Summer students -- Sasha
- - Olivia, Ben, and Shane are on site. Expect one student from Wuhan (have to start with the paperwork)
- - Projects: document all test results, assist with the cable/divider installation, install signal cables on patch panel, work on the ECAL monitoring plots
- Beam tests with the PS
- measure shower beam profile and reconstruction in the crystal/LG transition region
- (install prototype with 5x5 PbWO4 modules + ? LG)
- Other hardware projects
- prototype of the ECAL veto counter (?)
- Impact of veto on eta channels from Feb'24 collaboration meeting: File:P9.pdf
- prototype of the ECAL veto counter (?)
- FCAL2 posters for open house
- JEF/ECAL/FCAL poster (Laveen + students + feedback from all of us)
- JEF physics poster (Laveen)
- Analysis/Simulation