Line 14: | Line 14: | ||
* '''Ongoing projects''' -- Sasha, all | * '''Ongoing projects''' -- Sasha, all | ||
** Tested and labeled ~250 short signal cables | ** Tested and labeled ~250 short signal cables | ||
− | ** | + | ** Final inspection of installed lead glass and lead tungstate modules [https://logbooks.jlab.org/entry/4196869] |
** [https://halldweb.jlab.org/detectors/fcal2/installation/students_2023/list_of_students_2023.xlsx Summer Students (2023) ] | ** [https://halldweb.jlab.org/detectors/fcal2/installation/students_2023/list_of_students_2023.xlsx Summer Students (2023) ] | ||
* '''[[Testing of PMT dividers]]''' -- Sasha / Vlad | * '''[[Testing of PMT dividers]]''' -- Sasha / Vlad |
Revision as of 22:41, 12 October 2023
Meeting time and location:
- 9:30 am EST (JLab time) remote only
- Connection information
Agenda
- Preparation of parts for ECAL -- Sasha
- - signal cables: 1360 short cables, all long cables are ready
- - signal patch panels are ready
- - HV cables: 140 short cables (expect to receive most of them in 1-2 weeks), 36 long cables are in production
- - HV distribution boards: have not yet been ordered (need to check multi-pin connector layout)
- - LV cables: ordered, lead time unclear
- - LV distribution boards: have not yet been ordered (need to finalize design, meeting with Chris and Stephanie on Monday next week)
- - Optical fibers: received all
- Ongoing projects -- Sasha, all
- Tested and labeled ~250 short signal cables
- Final inspection of installed lead glass and lead tungstate modules [1]
- Summer Students (2023)
- Testing of PMT dividers -- Sasha / Vlad
- - Test setup is ready. About 30 dividers are ready for testing
- Installation of the FCAL2 detector & integration to GlueX -- Sasha / Vlad / Hakob
- Light monitoring system
- Analysis/Simulation