Difference between revisions of "JEF meeting, October 13, 2023"
From GlueXWiki
(→Agenda) |
|||
Line 8: | Line 8: | ||
** - signal patch panels are ready | ** - signal patch panels are ready | ||
** - HV cables: 140 short cables (expect to receive most of them in 1-2 weeks), 36 long cables are in production | ** - HV cables: 140 short cables (expect to receive most of them in 1-2 weeks), 36 long cables are in production | ||
− | ** - HV | + | ** - HV distribution boards: have not yet been ordered (need to check multi-pin connector layout) |
** - LV cables: ordered | ** - LV cables: ordered | ||
+ | ** - LV distribution boards: have not yet been ordered (need to finalize design, meeting with Chris and Stephanie on Monday next week) | ||
* '''[[Testing of PMT dividers]]''' -- Sasha / Vlad | * '''[[Testing of PMT dividers]]''' -- Sasha / Vlad | ||
* '''Installation of the FCAL2 detector & integration to GlueX''' -- Sasha / Vlad / Hakob | * '''Installation of the FCAL2 detector & integration to GlueX''' -- Sasha / Vlad / Hakob | ||
* '''Light monitoring system''' | * '''Light monitoring system''' | ||
*'''Analysis/Simulation''' | *'''Analysis/Simulation''' |
Revision as of 22:03, 12 October 2023
Meeting time and location:
- 9:30 am EST (JLab time) remote only
- Connection information
Agenda
- Preparation of parts for ECAL -- Sasha
- - signal cables: 1360 short cables, all long cables are ready
- - signal patch panels are ready
- - HV cables: 140 short cables (expect to receive most of them in 1-2 weeks), 36 long cables are in production
- - HV distribution boards: have not yet been ordered (need to check multi-pin connector layout)
- - LV cables: ordered
- - LV distribution boards: have not yet been ordered (need to finalize design, meeting with Chris and Stephanie on Monday next week)
- Testing of PMT dividers -- Sasha / Vlad
- Installation of the FCAL2 detector & integration to GlueX -- Sasha / Vlad / Hakob
- Light monitoring system
- Analysis/Simulation