+ | 9/1 Installation and survey until ~18:00 | ||
+ | 9/1 18:00 - 9/2 04:00 -- Straight-track data (10 hours) | ||
+ | 9/2 04:00 - 9/3 12:00 -- Ramp solenoid magnet (8 hours) | ||
+ | 9/3 12:00 - 9/4 06:00 -- Full field data: tracking mode (18 hours) | ||
+ | 9/4 06:00 - 9/5 10:00 -- Full field data: TRD mode | ||
+ | |||
+ | == Detector location and plane labeling == | ||
[https://halldweb.jlab.org/wiki/images/4/45/GEM_TRD_setup_Aug2020.pdf Lubomir's presentation] | [https://halldweb.jlab.org/wiki/images/4/45/GEM_TRD_setup_Aug2020.pdf Lubomir's presentation] | ||
Line 17: | Line 24: | ||
** 8 hours: standard FCAL-BCAL trigger for alignment data | ** 8 hours: standard FCAL-BCAL trigger for alignment data | ||
− | ==== Full | + | ==== Full-field data: tracking mode ==== |
* With the aligned GEM/TRD collect data for track extrapolation validation and multi-plane tracking directly upstream of DIRC | * With the aligned GEM/TRD collect data for track extrapolation validation and multi-plane tracking directly upstream of DIRC | ||
* Full solenoid field sample at the beam-center TRD positions with the full GEM readout for tracking and alignment studies | * Full solenoid field sample at the beam-center TRD positions with the full GEM readout for tracking and alignment studies | ||
** Standard GlueX running conditions at 150nA, 250 nA and 350nA | ** Standard GlueX running conditions at 150nA, 250 nA and 350nA | ||
** 2 hours: focused FCAL trigger in GEM location to verify TRD/GEM signals (raw mode) | ** 2 hours: focused FCAL trigger in GEM location to verify TRD/GEM signals (raw mode) | ||
− | ** 8 hours: standard FCAL-BCAL trigger | + | ** 8 hours: standard FCAL-BCAL trigger at 150 nA (low energy TAGH turned on) |
− | ** 4 hours: standard FCAL-BCAL trigger | + | ** 4 hours: standard FCAL-BCAL trigger at 250 nA (low energy TAGH turned off) |
− | ** 4 hours: standard FCAL-BCAL trigger | + | ** 4 hours: standard FCAL-BCAL trigger at 350 nA (low energy TAGH turned off) |
− | ==== Full | + | ==== Full-field data: TRD mode ==== |
* For TRD pion rejection performance acquire production samples with the TRD in "cluster counting" mode with all the GEM packages read out. | * For TRD pion rejection performance acquire production samples with the TRD in "cluster counting" mode with all the GEM packages read out. | ||
* Operate TRDs with two different gasses using raw mode (Lubomir and Sergey required) | * Operate TRDs with two different gasses using raw mode (Lubomir and Sergey required) | ||
** 4 hours: standard FCAL-BCAL trigger | ** 4 hours: standard FCAL-BCAL trigger |
Revision as of 08:10, 1 September 2020
Contents
Preliminary Schedule
9/1 Installation and survey until ~18:00 9/1 18:00 - 9/2 04:00 -- Straight-track data (10 hours) 9/2 04:00 - 9/3 12:00 -- Ramp solenoid magnet (8 hours) 9/3 12:00 - 9/4 06:00 -- Full field data: tracking mode (18 hours) 9/4 06:00 - 9/5 10:00 -- Full field data: TRD mode
Detector location and plane labeling
Calibration datasets
Summary page for Summer 2020 TRD/GEM Commissioning lists the relevant run ranges for the datasets collected below
Straight-track data
- For alignment of the GEM/TRD we need to acquire production samples with the magnetic field off
- Straight-track sample at the beam-center TRD positions with the full GEM readout for tracking and alignment studies
- Standard GlueX no-field measurements with 50nA on 10^-4 amorphous radiator
- 2 hours: focused FCAL trigger in GEM location to verify TRD/GEM signals (raw mode)
- 8 hours: standard FCAL-BCAL trigger for alignment data
Full-field data: tracking mode
- With the aligned GEM/TRD collect data for track extrapolation validation and multi-plane tracking directly upstream of DIRC
- Full solenoid field sample at the beam-center TRD positions with the full GEM readout for tracking and alignment studies
- Standard GlueX running conditions at 150nA, 250 nA and 350nA
- 2 hours: focused FCAL trigger in GEM location to verify TRD/GEM signals (raw mode)
- 8 hours: standard FCAL-BCAL trigger at 150 nA (low energy TAGH turned on)
- 4 hours: standard FCAL-BCAL trigger at 250 nA (low energy TAGH turned off)
- 4 hours: standard FCAL-BCAL trigger at 350 nA (low energy TAGH turned off)
Full-field data: TRD mode
- For TRD pion rejection performance acquire production samples with the TRD in "cluster counting" mode with all the GEM packages read out.
- Operate TRDs with two different gasses using raw mode (Lubomir and Sergey required)
- 4 hours: standard FCAL-BCAL trigger