Line 4: | Line 4: | ||
=Agenda= | =Agenda= | ||
*'''Preparation of parts for ECAL''' -- Sasha | *'''Preparation of parts for ECAL''' -- Sasha | ||
− | ** - signal cables | + | ** - signal cables and 2 patch panels [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/10_13_2023/signal_patch_panel.jpg ] - done |
− | + | ** - HV short cables: done | |
− | ** - HV short cables: | + | |
** - HV long cable, 18 ready (out of 36) | ** - HV long cable, 18 ready (out of 36) | ||
− | ** - HV distribution boards: | + | ** - HV distribution boards: not designed |
− | ** - LV cables: waiting for about | + | ** - LV cables: waiting for about 20 cables |
− | ** - LV distribution boards [https://halldweb.jlab.org/detectors/fcal2/cables/lv_distribution/lv_dist_board.jpg ]. | + | ** - LV distribution boards [https://halldweb.jlab.org/detectors/fcal2/cables/lv_distribution/lv_dist_board.jpg ]. One board out of 4 is ready |
− | ** - | + | ** - LED: the prototype of the LED board has been received. Chris will populate it with components |
* '''Ongoing projects''' | * '''Ongoing projects''' | ||
− | |||
** - [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/05_10_2024/May-10-2024-L.pdf Update from Laveen] | ** - [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/05_10_2024/May-10-2024-L.pdf Update from Laveen] | ||
+ | ** - Testing, labeling and bundling LV cables | ||
* '''[[Testing of PMT dividers]]''' -- Sasha / Vlad / George / Mindy | * '''[[Testing of PMT dividers]]''' -- Sasha / Vlad / George / Mindy | ||
** - Testing procedure [https://halldweb.jlab.org/detectors/fcal2/dividers/divider_test_guide.pptx] | ** - Testing procedure [https://halldweb.jlab.org/detectors/fcal2/dividers/divider_test_guide.pptx] | ||
− | |||
** - All dividers have been fabricated and tested by George [https://halldweb.jlab.org/wiki/index.php/Final_test_of_dividers] | ** - All dividers have been fabricated and tested by George [https://halldweb.jlab.org/wiki/index.php/Final_test_of_dividers] | ||
− | *** | + | *** Continue removing regulators from the PCB |
− | + | ||
* '''Installation of the FCAL2 detector & integration to GlueX''' -- Sasha / Vlad / Hakob / Laveen | * '''Installation of the FCAL2 detector & integration to GlueX''' -- Sasha / Vlad / Hakob / Laveen | ||
** <span style="color: red"> Installation of the LMS has been completed </span> [https://logbooks.jlab.org/entry/4282307] | ** <span style="color: red"> Installation of the LMS has been completed </span> [https://logbooks.jlab.org/entry/4282307] |
Revision as of 08:28, 10 May 2024
Meeting time and location:
- 9:30 am EST (JLab time) remote only
- Connection information
Agenda
- Preparation of parts for ECAL -- Sasha
- - signal cables and 2 patch panels [1] - done
- - HV short cables: done
- - HV long cable, 18 ready (out of 36)
- - HV distribution boards: not designed
- - LV cables: waiting for about 20 cables
- - LV distribution boards [2]. One board out of 4 is ready
- - LED: the prototype of the LED board has been received. Chris will populate it with components
- Ongoing projects
- - Update from Laveen
- - Testing, labeling and bundling LV cables
- Testing of PMT dividers -- Sasha / Vlad / George / Mindy
- Installation of the FCAL2 detector & integration to GlueX -- Sasha / Vlad / Hakob / Laveen
- Installation of the LMS has been completed [5]
- Installation and testing cables and dividers [6][7]
- All crates are connected to the network switch Ethernet switch [8]
- Preparing for testing installed dividers
- Detector installation page
- Preparation for beam tests with the PS
- measure shower beam profile
- shower reconstruction between PbWO4 and LG
- Other hardware projects
- --prototype of the ECAL veto counter
- --study shower profile using PS (also transition region between lead tungstate and LG modules (?) )
- FCAL2 poster for open house?
- JEF/ECAL/FCAL poster
- Analysis/Simulation