JEF meeting, May 19, 2023
From GlueXWiki
Meeting time and location:
- 9:30 am EST (JLab time) remote only
- Connection information
Agenda
- Preparation for the ECAL installation [1]
- Preparation of parts for FCAL2 modules -- Sasha
- Crystals:
- Received 40 crystals from CRYTUR [2], 10 have been recently sent out. Remaining 45 crystals.
- Wrapped crystals: 10
- Available for wrapping: 10 SICCAS + 5 CRYTUR = 15
- George (DSG group) finished with preshaping.
- More than 400 long signal cables received, can start checking, bundling, labeling (receive labeling machine in a couple of weeks)
- Procurement parts for the LMS
- 16,400 ft of optical fibers delivered to the lab. 7,600 will be delivered in September.
- Receive first batch of donats for the LMS, evrth. looks Ok. Will receive all of them in a couple of weeks (start working on the LMS)
- Crystals:
- Module fabrication -- Sasha
- Fabricated modules: Total 1542
- 9 modules fabricated during last week
- Available for fabrication: 26
- 42 modules fabricated using 'low quality' crystals for the stacking mockup and 'crunch' tests.
- Report from students
- Fabricated modules: Total 1542
- Visual inspections of fabricated modules [3]
- 160 modules checked [4]
- Testing of PMT dividers -- Sasha / Vlad / Arshak
- FCAL2 modules with dividers installed on the CCAL [5]
- Met with Vlad P. on Tuesday. Fine tuned the divider circuit. Checking/tuning an amplifier; Chris S. ordered some OPS.
- Installation of the FCAL2 detector & integration to GlueX -- Sasha / Arshak
- Detector installation page
- Updates from the meetings with Tim's group [6]
- Discussion of the FCAL2 installation procedures [7]
- Final mapping of low-voltage cables
- Manpower and division of tasks
- Projects for summer students
- Summer Students (2023)
- Light monitoring system -- Arshak
- Simulations/Analysis
Minutes
Attendees: Bill, Igal, Jane, Sasha, Igor, Arshak, Zisis, Jon, Eugene, Susan, S.T.
- 40 new Crytur crystals arrived
- 15 crystals ready for wrapping
- Cable labeling machine arrived
- Most fibers for LMS arrived
- Need optimize length
- Need to glue fibers into donuts
- Remaining fibers to arrive in September?
- Total number of fabricated modules = 1542
- 26 crystals ready for fabrication
- Students doing module inspection -- some issues found (tedlar, PMT alignment,brazing quality,..)
- Sticky kapton tape added to mitigate cold soldering on brazing joint
- Preparing for mock-up to study module stacking in ISB
- PMT divider design finalized (change op-amp and part of resistor chain)
- No longer saturates at 1.6 V -- can use with 2V range of fADC
- Can run at nominal HV
- Base fabrication lead time ~4 weeks
- All LG blocks have been removed from existing FCAL frame -- some LG blocks need refurbishment
- Arshak setting up scanner for LMS fibers based on Labview program
- Arshak borrowed fiber polisher from Hall B