GlueX Target Meeting, May 22, 2014

From GlueXWiki
Jump to: navigation, search

Present: Chris Keith, Dave Meekins, Josh Pierce, James Brock, Matt Marchlik, Dave Butler, Alexandre Deur, Tim Whitlatch

Minutes from last mtg https://halldweb.jlab.org/wiki/index.php/GlueX_Target_Design_Mtg,_Apr_21,_2014

Agenda

  • Where are we now? Media:Target labor.pdf
  • Cryo hardware status
  • Gas system status
    • Exhaust from pressure relief
    • Plumbing on cart
    • pressure system documentation
    • Storage tanks
  • 3D model/drawings Media:Target assy.pdf
  • Target/Start counter interface
  • Vacuum system update
    • Flange config
  • Controls status
    • updated P&I
    • changes for subcooled config
  • Installation cart update Media:Target cart.jpg
    • Tank config
    • Lifting
    • Controls/panel config
    • Alignment features
  • Scattering chamber status
  • Cell Fabrication Status
    • thermometry
    • Spare cell
  • Schedule
    • Readiness review
    • Assy/test in EEL
    • Install/test in Hall

Info


Minutes

  • James fabricating new cell with straight torlon base and aluminized Kapton(plus a spare) - should be done 1 week
  • Hub drilled and match pinned w/ Start counter
  • Tom to run cable for kill switch in counting room
  • Gas panel almost complete
  • additional 80/20 ordered for cart to mount vacuum pumps
  • Vent stack materials in house
  • Power for compressor installed
  • Hall D to design 5 mil kapton window cartridge for target vacuum
  • Start Counter patch panel to be mounted on cart (4.5' cables)
  • Align target to aluminum tube Fiducialize target vacuum cross
  • Need to locate heat exch.
  • Hall D to run cable to flow and temp. switches from chilled water, 3 leads ea. 22 guage
  • PLC controls to be set up in EEL. need to develop expert GUI - alarms only
  • Labview code needed to start/stop compressor- RS22
  • Hall D to supply control air for gate valve and Nitrogen line for purging
  • Dave M. has low flow regulator for nitrogen vent stack purge
  • Dave B. making cables for PLC to cart. PLCs will be located in rack on the north side
  • Chris writing test procedure for EEL
  • Dave M making manifold for nitrogen purge.