GlueX Target Design Mtg, July 10, 2013
From GlueXWiki
Present: Dave Meekins, Jim Fochtman, Mark Ito, Josh Pierce, Tim Whitlatch,
Agenda
- Floyd taking over for Hall D
- Review notes from last mtg
- Jim Design details
- Fabrication update
- Controls update
- Gas panel update
Info
- P&I Diagram Media:Target P&I.pdf
- Controls logic Media:Target controls.pdf
- Dave's SOW Media:Target new SOW.pdf
- Dave's Calcs Media:Target calcs1.pdf Media:Target calcs2.pdf
- Dave's FMEA Media:Target latest FMEA.pdf
Notes from last week
- Gas panel, all ordered, waiting on relief valves and pressure switch
- Hall D will take care of cart design and analysis, need panel/cart interface
- Work on shielding/fill tube design, most decisions made
- Scattering chamber design done, will be glue, need dwgs, will be aluminum for test, rohacel/Dp190 for production.
- Need to review FMEA
- Look at design for next mtg
- Alum target base is made - Mark needs to ok for physics
- All drawings will be released through Hall D. Hall D will assign numbers.
- Piping for vent waiting on final design. 2" tube , 5' above roof line.Kausch to sign vent dwgs
- Gas panel needs PT inspection, need as built drawings