Difference between revisions of "Run Planning Meeting Notes, June 23 - June 29, 2022"

From GlueXWiki
Jump to: navigation, search
(Thursday June 23)
Line 8: Line 8:
  
 
[https://docs.google.com/spreadsheets/d/1sdluzy7p5vnlhw9AWJHBrYbXKTBet45o4den4zWX9dc/edit#gid=1855021251 Spreadsheet with list of runs]
 
[https://docs.google.com/spreadsheets/d/1sdluzy7p5vnlhw9AWJHBrYbXKTBet45o4den4zWX9dc/edit#gid=1855021251 Spreadsheet with list of runs]
 +
 +
 +
=Friday June 24=
 +
 +
#Last 24h:
 +
#*Accelerator went down at 6:20 as planned.
 +
#*RF recovery coupled with trying to get more beam to Hall C did not go well. We were promised beam after 5pm, then 7, then 1030.
 +
#Shift Summaries
 +
#*
 +
#Reports
 +
#*[https://logbooks.jlab.org/entry/4006381 Bleedthrough prediction from Hovanes]
 +
#Issues
 +
#Plans
 +
#*Sasha - check straight target configuration
 +
#*Sasha - make new CPP configuration as requested by email
 +
#*Richard (if not done during owl) - repeat 2 rows in microscope scan
 +
#*Return to production. Cycle through 240M events for each of 45perp, 45perp, 135para, 135para, then 60M events on the AMO on the goniometer.
 +
#*Production as above should be our default for 6d, with 1d on empty target.
 +
#*Try again for the TAC run on Friday
 +
#Commissioning steps temporarily postponed:
 +
#*Flux optimization/Act .Col. calibration
 +
#*Bleed-through test: measure bleed-through with A slit as usual and A slit completely closed to see whether using B slit would help.
 +
 +
  
 
=Thursday June 23=
 
=Thursday June 23=
Line 29: Line 53:
 
#* [https://logbooks.jlab.org/entry/4006157 DAQ crash ROCTRIG2 - called Sergey]
 
#* [https://logbooks.jlab.org/entry/4006157 DAQ crash ROCTRIG2 - called Sergey]
 
#* [https://logbooks.jlab.org/entry/4006217 DAQ lost comms with ROCBCAL11 - stop & restart DAQ fixed this]
 
#* [https://logbooks.jlab.org/entry/4006217 DAQ lost comms with ROCBCAL11 - stop & restart DAQ fixed this]
#* [https://logbooks.jlab.org/entry/4006229 AD00C x position moving]
+
#* [https://logbooks.jlab.org/entry/4006229 AD00C x position moving] probably due to beam energy changing
 
#* (Tagger NMR)
 
#* (Tagger NMR)
 
#* (DIRC sensor)
 
#* (DIRC sensor)

Revision as of 21:51, 23 June 2022

↑ Back to Run Coordination Meetings:Summer2022

Meeting are via ZoomGov: connect (Meeting ID: 160 199 0060 / Passcode 8394)

MCC whiteboard

Hall D counting room white board

Spreadsheet with list of runs


Friday June 24

  1. Last 24h:
    • Accelerator went down at 6:20 as planned.
    • RF recovery coupled with trying to get more beam to Hall C did not go well. We were promised beam after 5pm, then 7, then 1030.
  2. Shift Summaries
  3. Reports
  4. Issues
  5. Plans
    • Sasha - check straight target configuration
    • Sasha - make new CPP configuration as requested by email
    • Richard (if not done during owl) - repeat 2 rows in microscope scan
    • Return to production. Cycle through 240M events for each of 45perp, 45perp, 135para, 135para, then 60M events on the AMO on the goniometer.
    • Production as above should be our default for 6d, with 1d on empty target.
    • Try again for the TAC run on Friday
  6. Commissioning steps temporarily postponed:
    • Flux optimization/Act .Col. calibration
    • Bleed-through test: measure bleed-through with A slit as usual and A slit completely closed to see whether using B slit would help.


Thursday June 23

  1. Last 24h:
  2. Shift Summaries
  3. Reports
    • From MCC: Reminder that 911 from lab phone is forwarded to normal 911 and also automatically informs the crew chief, guard shack, etc that there's an emergency, crew are CPR qualified & have AED. This doesn't happen from RC phones (or cellphones). No problem w 911 from other phone; if there's a lab phone handy it saves some time.
    • Power shed 3-4pm today, beam restoration likely 5pm+.
    • MCC planning to raise the current to Hall C.
  4. Issues
  5. Plans
    • No beam until swing.
    • Walk-through at 11am
    • Site exit opposite Tech Center closed most of the day - need to exit by resfac or Lidl.
    • Put the target back (done).
    • Sasha - check straight target configuration.
    • Sasha - make new CPP configuration as requested by email
    • Richard - repeat 2 rows in microscope scan
    • Return to production. Cycle through 240M events for each of 45perp, 45perp, 135para, 135para, then 60M events on the AMO on the goniometer.
    • Production as above should be our default for 6d, with 1d on empty target.
    • Try again for the TAC run on Friday evening
  6. Commissioning steps temporarily postponed:
    • Flux optimization/Act .Col. calibration
    • Bleed-through test: measure bleed-through with A slit as usual and A slit completely closed to see whether using B slit would help.