Run Planning Meeting Notes, December 16 - December 22, 2021

From GlueXWiki
Revision as of 08:00, 17 December 2021 by Deurpam (Talk | contribs) (Friday December 17)

Jump to: navigation, search

Friday December 17

  1. Last 24h:
    • Smooth production on LD2 at 140 nA, 0/90 para and perp. Took one amorphous run (90578).
  2. Issues
  3. Plans
    • Continue running on LD2 at 140 nA, 0/90 para and perp until 1:45pm (if empty target run is needed) or 3:45pm (if not).
    • Target change LD2 → L4He:
      • If an empty target run is desirable, start emptying the target and turn off pulse refrigerator at 1:45pm (assuming a 2h run). Otherwise, start emptying/pulse refr. off at 3:45pm.
      • 2pm-4pm: 2h empty target run?
      • 4pm. Ask MCC for beam off and Rapid Access. Chris Carlin goes in the Hall to start switching gas. Solenoid will stay on: be aware of magnetic field fringes.
      • Between 5pm and 6pm: Chris is done switching gas. End of rapid access.
      • Ask for beam. (No need for beam restoration check as the beam down time is small): while the target cools down (about 3h process). A. Somov will take test data.
    • around 9pm: target is cold. Start running on L4He at 150 nA, 0/90 para and perp.

Thursday December 16

  1. Last 24h:
    • Smooth production on LD2 at 140 nA, 0/90 para and perp. Interrupted only by search for better spot on diamond (~1h see below) and ~1h of RF-related down time.
    • Spectra from A. Somov.
  2. Issues
  3. Plans
    • Continue running on LD2 at 140 nA, 0/90 para and perp. Do one amorphous run today.
    • Discussion on possible target change to L4He.
    • Status of possible CPP test.