Difference between revisions of "Run Planning Meeting Notes, December 16 - December 22, 2021"

From GlueXWiki
Jump to: navigation, search
(Thursday December 16)
(Thursday December 16)
Line 9: Line 9:
 
#* Rates are ~10% lower compared to previous LD<sub>2</sub> data taking period, see [https://halldweb.jlab.org/wiki/images/a/a3/Rate.png here]. Part of it is lower transmission but even accounting for this, normalized rates remains 6% lower (see trigger/PS, black disk symbols,  [https://halldweb.jlab.org/wiki/images/d/da/Rates_ratios.png here]).
 
#* Rates are ~10% lower compared to previous LD<sub>2</sub> data taking period, see [https://halldweb.jlab.org/wiki/images/a/a3/Rate.png here]. Part of it is lower transmission but even accounting for this, normalized rates remains 6% lower (see trigger/PS, black disk symbols,  [https://halldweb.jlab.org/wiki/images/d/da/Rates_ratios.png here]).
 
#Plans
 
#Plans
#* Continue running on LD<sub>2</sub> at 140 nA, 0/90 para and perp.
+
#* Continue running on LD<sub>2</sub> at 140 nA, 0/90 para and perp. Do one amorphous run today.
 
#* Discussion on possible target change to L<sup>4</sup>He.  
 
#* Discussion on possible target change to L<sup>4</sup>He.  
 
#* Status of possible CPP test.
 
#* Status of possible CPP test.

Revision as of 15:44, 16 December 2021

Thursday December 16

  1. Last 24h:
    • Smooth production on LD2 at 140 nA, 0/90 para and perp. Interrupted only by search for better spot on diamond (~1h see below) and ~1h of RF-related down time.
    • Spectra from A. Somov.
  2. Issues
  3. Plans
    • Continue running on LD2 at 140 nA, 0/90 para and perp. Do one amorphous run today.
    • Discussion on possible target change to L4He.
    • Status of possible CPP test.