Photon Beam Commissioning Discussion July 23, 2014

From GlueXWiki
Revision as of 13:33, 23 July 2014 by Michaelm (Talk | contribs) (Agenda)

Jump to: navigation, search

Organization

  • Time: 4 pm EST
  • Connecting: detailed instructions are here
  • Conference id: 536076821

References

Action Items

  • Send Todd a geometry of tagger area, including the mapped tagger magnet field, for GEANT simulations (Richard). Sasha says he will do this
  • Estimate rates and ranges of parameters needed for the photon beam tuning (Todd for accelerator; Elton, Hovanes, Alexandre for Hall D)

Agenda

  1. Announcements
  2. Electron Commissioning (Todd/Mike)
    • The Hall D Beam Delivery Procedure is heading toward Rev. 10 with the feedback which was received.
    • Ion Chamber Procedures are currently under review for release and use.
    • Eugene/Curtis added as administrators for Hall D Operational Restrictions[1]
    • System Experts requested to write test plans for nA BPM, FFB, and Active Collimator hardware commissioning.
    • Cross Calibration Procedure for absolute current measurement desired?
    • Point of contact in Radcon for measurement test plan for fall? (George or Pavel perhaps?)
    • Regarding minimum deliverable current (open question from last time):
Stripline BPM Resolutions ≥ 30nA 100um resolution < 30nA resolution suffers(position noisy barring additional filtering) 3nA yields expected resolution ≈ 300 µm
  1. Photon Commissioning Draft (Alexandre)
  2. Radiation monitors
  3. Aug 8 Review:
  4. Other business

Minutes

Attending:'