#*Ion Chamber Procedures are currently under review for release and use.
 
#*Ion Chamber Procedures are currently under review for release and use.
 
#*Eugene/Curtis have been added as administrators for Hall D's Operational Restrictions[http://opsweb.acc.jlab.org/internal/ops/ops_webpage/restrictions/ops_restrictions.html]
 
#*Eugene/Curtis have been added as administrators for Hall D's Operational Restrictions[http://opsweb.acc.jlab.org/internal/ops/ops_webpage/restrictions/ops_restrictions.html]
#*System Experts requested to write test plans for nA BPM, FFB, and Active Collimator hardware commissioning.  
+
#*System Experts have been requested to write test plans for hardware commissioning of the nA BPMs, FFB system, and the Active Collimator.
#*Cross Calibration Procedure for absolute current measurement desired?
+
#*Is a Cross Calibration Procedure for absolute current measurement desired? (Between Faraday Cup 2 in the Injector and the Hall BCM)
#*Point of contact in Radcon for measurement test plan for fall? (George or Pavel perhaps?)
+
#*Need to identify the appropriate point of contact in Radcon to write the measurement test plan for fall (George K. or Pavel perhaps?)
 
#*Regarding minimum deliverable current (open question from last time):  
 
#*Regarding minimum deliverable current (open question from last time):  
 
{| class="wikitable" style="text-align: center; color: black;"
 
{| class="wikitable" style="text-align: center; color: black;"

Revision as of 13:37, 23 July 2014

Organization

  • Time: 4 pm EST
  • Connecting: detailed instructions are here
  • Conference id: 536076821

References

Action Items

  • Send Todd a geometry of tagger area, including the mapped tagger magnet field, for GEANT simulations (Richard). Sasha says he will do this
  • Estimate rates and ranges of parameters needed for the photon beam tuning (Todd for accelerator; Elton, Hovanes, Alexandre for Hall D)

Agenda

  1. Announcements
  2. Electron Commissioning (Todd/Mike)
    • The Hall D Beam Delivery Procedure is heading toward Rev. 10 with the feedback which was received.
    • Ion Chamber Procedures are currently under review for release and use.
    • Eugene/Curtis have been added as administrators for Hall D's Operational Restrictions[1]
    • System Experts have been requested to write test plans for hardware commissioning of the nA BPMs, FFB system, and the Active Collimator.
    • Is a Cross Calibration Procedure for absolute current measurement desired? (Between Faraday Cup 2 in the Injector and the Hall BCM)
    • Need to identify the appropriate point of contact in Radcon to write the measurement test plan for fall (George K. or Pavel perhaps?)
    • Regarding minimum deliverable current (open question from last time):
Stripline BPM Resolutions ≥ 30nA 100um resolution < 30nA resolution suffers(position noisy barring additional filtering) 3nA yields expected resolution ≈ 300 µm
  1. Photon Commissioning Draft (Alexandre)
  2. Radiation monitors
  3. Aug 8 Review:
  4. Other business

Minutes

Attending:'